Agency Milestone Date of 06/05/2023 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Description:
Bonanza Solar, LLC submitted a right-of-way application for the Bonanza Solar Project to the Bureau of Land Management on December 4, 2020. The application indicated that a plan of development, required for right-of-way applications, would be submitted within 60 days of the application filing. A preliminary plan of development for the Bonanza Solar Project was submitted on March 5, 2021 and an updated version was provided on August 22, 2022.
On April 26, 2023 the BLM determined that it is appropriate to continue processing the right-of-way application, and it will be processed in accordance with the National Environmental Policy Act (NEPA), National Historic Preservation Act (NHPA), Endangered Species Act (ESA), and all other relevant laws, regulations, and policies.
Milestones:
Public scoping is the first formal public participation opportunity for the Bonanza Solar Project. The 45-day public scoping period was initiated when the Bureau of Land Management (BLM) publishes a Notice of Intent (NOI) in the Federal Register on June 5, 2023. During the scoping period, the BLM will host in-person and virtual workshops. The purpose of scoping is to provide the public with early information on the Applicants' Proposed Action as described in their Preliminary Plan of Development, identify preliminary issues, describe an agency preliminary purpose and need, initial range of alternatives, planning criteria, and information from baseline studies that may have been completed prior to scoping. The scoping period ends on July 20, 2023. After the scoping period, the BLM will publish as scoping report that categorizes the comments that were received.
-
Monthly Status Report for October 2026:The ROD will be signed on 11/20/2026
-
Monthly Status Report for September 2026:On 08/21/2026, the BLM published the NOA for the FEIS and PRPM Amendment for the Bonanza Solar Project in Clark and Nye counties, Nevada. The 30-day protest period ends 09/01/2026, followed by the BLM’s NEPA review and response to protests. The Governor’s Consistency Review is expected by 10/20/2026; the BLM will also evaluate comments and revise the documents as appropriate.
-
Monthly Status Report for August 2026:The Notice of Availability for the Final Environmental Impact Statement was published on August 21, 2026, which is much earlier than expected. The public review period is scheduled to end on September 21, 2026. The Record of Decision date is anticipated to be October 20, 2026 to allow for the necessary time to respond to comments.
-
Monthly Status Report for July 2026:The BLM is working in coordination with the project sponsor to update the target dates.
-
Monthly Status Report for June 2026:The BLM is working in coordination with the project sponsor to update the target dates.
-
Monthly Status Report for May 2026:The BLM is working in coordination with the project sponsor to update the target dates.
-
Monthly Status Report for April 2026:For the effective administration of public lands, the BLM needs to extend the release of the Notice of Availability of the Final Environmental Impact Statement (EIS) publication in the Federal Register to December 7, 2027. The Draft EIS identified indirect, direct, and cumulative impacts that necessitated communication with cooperating agencies, additional time is needed to further refine and reinforce the design features.
-
Monthly Status Report for March 2026:For the effective administration of public lands, the BLM needs to extend the release of the Notice of Availability of the Final Environmental Impact Statement (EIS) publication in the Federal Register to December 7, 2027. The Draft EIS identified indirect, direct, and cumulative impacts that necessitated communication with cooperating agencies, additional time is needed to further refine and reinforce the design features.
-
Monthly Status Report for February 2026:For the effective administration of public lands, the BLM needs to extend the release of the Notice of Availability of the Final Environmental Impact Statement (EIS) publication in the Federal Register to December 7, 2027. The Draft EIS identified indirect, direct, and cumulative impacts that necessitated communication with cooperating agencies, additional time is needed to further refine and reinforce the design features.
-
Monthly Status Report for January 2026:Due to items identified in the Draft EIS, the EIS is now expected to be complete in April of 2028.
-
Monthly Status Report for December 2025:BLM plans to release of the Notice of Availability of the Final Environmental Impact Statement (EIS) publication in the Federal Register to December 7, 2027. The Draft EIS identified indirect, direct, and cumulative impacts that necessitated further communication with cooperating agencies, additional time is needed to further refine and reinforce the design features.
-
Monthly Status Report for November 2025:The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
-
Monthly Status Report for October 2025:The Department of the Interior-Bureau of Land Management internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. BLM is working towards meeting required enhanced coordination and reviews.
-
Monthly Status Report for September 2025:The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project. The Bureau is awaiting guidance and direction from DOI regarding if or when an NOA may be published.
-
Monthly Status Report for August 2025:The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
-
Monthly Status Report for July 2025:The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
-
Non-conformance Explanation:The Bureau of Land Management (BLM) missed the June 5, 2025 milestone to publish the Final Environmental Impact Statement (FEIS). Per 42 U.S.C.§ 4370m-2(c)(2)(F), BLM is required to provide an alternative completion date and an initial explanation for the missed completion date by June 13, 2025. BLM has provided the initial explanation for the missed date, but has not yet provided the required alternative completion date. The Executive Director is working directly with BLM leadership to ensure an alternative completion date is determined and represented on the permitting timetable as soon as possible. The DOI-BLM internal review and briefing process is occurring during a transition period for new Bureau and Department leadership. As such, the review of the project is requiring enhanced coordination that has affected the timeline for this project.
Public scoping is the first formal public participation opportunity for the Bonanza Solar Project. The 45-day public scoping period was initiated when the Bureau of Land Management (BLM) publishes a Notice of Intent (NOI) in the Federal Register on June 5, 2023. During the scoping period, the BLM will host in-person and virtual workshops. The purpose of scoping is to provide the public with early information on the Applicants' Proposed Action as described in their Preliminary Plan of Development, identify preliminary issues, describe an agency preliminary purpose and need, initial range of alternatives, planning criteria, and information from baseline studies that may have been completed prior to scoping. The scoping period ends on July 20, 2023. After the scoping period, the BLM will publish as scoping report that categorizes the comments that were received.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/19/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
Bonanza Solar, LLC proposes to construct, operate, and decommission a 300 MW solar photovoltaic and battery energy storage system electrical generation plant and associated facilities on approximately half of the 5,133 acre "application area". The project proposes to include:
- A main access road;
- A secondary access for emergency purposes;
- A 5.5 mile 230 kV gen-tie;
- Power blocks of electrical generating capacity;
- Power collection and power conversion systems;
- Battery energy storage system;
- An on-site electrical substation;
- An on-site operations and maintenance building;
- Temporary construction laydown areas within the project fence line;
- A roadway system consisting of internal and perimeter roadways within the project fence line;
- Microwave/communication tower;
- Site security, fencing, and lighting; and
- Meteorological stations.
The proposed project site is entirely on land administered by the Bureau of Land Management, Southern Nevada District. The proposed project would be on Solar Variance lands as identified in the 2012 Final Programmatic Environmental Impact Statement for Solar Energy Development in Six Southwestern States (Solar PEIS).
Public scoping is the first formal public participation opportunity for the Bonanza Solar Project. The 45-day public scoping period was initiated when the Bureau of Land Management (BLM) publishes a Notice of Intent (NOI) in the Federal Register on June 5, 2023. During the scoping period, the BLM will host in-person and virtual workshops. The purpose of scoping is to provide the public with early information on the Applicants' Proposed Action as described in their Preliminary Plan of Development, identify preliminary issues, describe an agency preliminary purpose and need, initial range of alternatives, planning criteria, and information from baseline studies that may have been completed prior to scoping. The scoping period ends on July 20, 2023. After the scoping period, the BLM will publish as scoping report that categorizes the comments that were received.