Agency Milestone Date of 07/31/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Milestones:
-
Non-conformance Explanation:The NOI for the Silver Rock Transmission Line Project began routing with BLM Utah and Nevada on June 3, 2026, and was sent to the BLM Headquarters on June 23, 2026. The BLM Headquarters created a new routing on June 25, 2026. The DOI review process of the NOI package has taken longer than expected which resulted in the missed date for NOI publication. BLM can not publish the NOI for the Silver Rock Transmission Project in the Federal Register until the DOI review process completes. BLM continues to engage with upper leadership to respond to information requests and communicate the importance of timely publication of the NOI. BLM intends to publish the NOI on or before the alternative completion date of August 28.
-
Non-conformance Explanation:The NOI for the Silver Rock Transmission Line Project began routing with BLM Utah and Nevada on June 3, 2026, and was sent to the BLM Headquarters on June 23, 2026. The BLM Headquarters created a new routing on June 25, 2026. The DOI review process of the NOI package has taken longer than expected which resulted in the missed date for NOI publication. BLM can not publish the NOI for the Silver Rock Transmission Project in the Federal Register until the DOI review process completes. BLM continues to engage with upper leadership to respond to information requests and communicate the importance of timely publication of the NOI. BLM intends to publish the NOI on or before the alternative completion date of August 28.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of War
Department of the Interior, Bureau of Reclamation
Description:
Silver Rock Transmission proposes to construct a large-scale high voltage transmission line to cross approximately 330-miles of public land to help facilitate BLM's geothermal leasing activities in eastern Nevada and western Utah by providing a viable transmission path to market for next-generation geothermal developments, thereby supporting federal leasing objectives and unlocking access to high-capacity baseload resources. The project would be constructed to transfer a nominal voltage of up to 600 kilovolts (kV) located within a siting corridor of approximately 1,000 feet.
-
Non-conformance Explanation:The NOI for the Silver Rock Transmission Line Project began routing with BLM Utah and Nevada on June 3, 2026, and was sent to the BLM Headquarters on June 23, 2026. The BLM Headquarters created a new routing on June 25, 2026. The DOI review process of the NOI package has taken longer than expected which resulted in the missed date for NOI publication. BLM can not publish the NOI for the Silver Rock Transmission Project in the Federal Register until the DOI review process completes. BLM continues to engage with upper leadership to respond to information requests and communicate the importance of timely publication of the NOI. BLM intends to publish the NOI on or before the alternative completion date of August 28.