Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-31-2026 07-31-2026 09-03-2026 Yes
Scoping (Agency Action) 08-31-2026 08-31-2026 10-05-2026 Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-25-2027 06-25-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-28-2028 04-28-2028 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-28-2028 07-28-2028 --- No
In Progress
Due to delays caused by the extended Department of the Interior (DOI) review process, the Notice of Intent (NOI) for the Silver Rock Transmission Line Project was published in the Federal Register later than planned, on September 3, 2026. This delay resulted in the NOI being released six days past the alternate target date, and the scoping period extension reflects the 30-day scoping window in the NOI. Scoping activities are currently ongoing., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-31-2026 07-31-2026 09-03-2026 Yes
Scoping (Agency Action) 08-31-2026 08-31-2026 10-05-2026 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-25-2027 06-25-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-28-2028 04-28-2028 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-28-2028 07-28-2028 --- No
Planned
The NOI for the Silver Rock Transmission Line Project began routing with BLM Utah and Nevada on June 3, 2026, and was sent to the BLM Headquarters on June 23, 2026. The BLM Headquarters created a new routing on June 25, 2026, The DOI review process of the NOI package has taken longer than expected which resulted in the missed date for NOI publication. BLM can not publish the NOI for the Silver Rock Transmission Project in the Federal Register until the DOI review process completes. BLM continues to engage with upper leadership to respond to information requests and communicate the importance of timely publication of the NOI. BLM intends to publish the NOI on or before the alternative completion date of August 28.", basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-31-2026 07-31-2026 08-28-2026 No
Scoping (Agency Action) 08-31-2026 08-31-2026 09-28-2026 No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-25-2027 06-25-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-28-2028 04-28-2028 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-28-2028 07-28-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 07-31-2026 07-31-2026 --- No
Scoping (Agency Action) 08-31-2026 08-31-2026 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 06-25-2027 06-25-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 04-28-2028 04-28-2028 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-28-2028 07-28-2028 --- No