Permitting Action Modification History

Complete
FWS concluded ESA Consultation ahead of schedule due to the completeness of the consultation package provided by NTIA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-25-2025 07-25-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-22-2025 08-14-2025 --- Yes
ESA Consultation Concludes (Agency Action) 12-15-2025 09-18-2025 --- Yes
In Progress
USFWS provided a letter on August 14, 2025, confirming receipt of a complete consultation package to initiate Section 7 consultation.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-25-2025 07-25-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-22-2025 08-14-2025 --- Yes
ESA Consultation Concludes (Agency Action) 12-15-2025 12-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-25-2025 07-25-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-22-2025 08-22-2025 --- No
ESA Consultation Concludes (Agency Action) 12-15-2025 12-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-25-2025 07-25-2025 --- No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) 08-22-2025 08-22-2025 --- No
ESA Consultation Concludes (Agency Action) 12-15-2025 12-15-2025 --- No