FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Request Package Submitted (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 07/08/2026 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Drue DeBerry
POC Title:
Deputy ARD

Description:

Pursuant to Section 7 of the Endangered Species Act, USFWS will consult with USACE on any project-related activities that may affect listed species or critical habitat.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Non-conformance Explanation:
    Internal coordination among USACE 408 and Regulatory as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the ESA action area.  This delay resulted in a domino effect to subsequent milestones.  Informal ESA consultation is anticipated with no change to final completion date until complete ESA submission is determined.
Current Target Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Non-conformance Explanation:
    Internal coordination among USACE 408 and Regulatory as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the ESA action area.  This delay resulted in a domino effect to subsequent milestones.  Informal ESA consultation is anticipated with no change to final completion date until complete ESA submission is determined.
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/12/2027

0 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of War Seal

LEAD AGENCY
Department of War, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

The Santee Sioux Tribe proposes the construction of a 41-mile, approximately 10-inch diameter water transmission line, along with necessary infrastructure, to deliver clean and reliable water to the Santee Sioux Nation located in Knox County, Nebraska. By constructing a 41-mile pipeline to interconnect the Santee system with that of Randall Community Water District and their existing surface water supply from Lake Francis Case in South Dakota, the Tribe will eliminate their water emergency and provide an opportunity for the next seven generations to continue to live on their lands provided under Executive Order in 1866.

USDA previously served as the facilitating agency for FAST-41.  In February 2026, USACE was deemed the lead agency. 

 
field_status
System Comments
Agency Milestone Date of 07/08/2026 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Approver Comments
<p>Internal coordination among USACE 408 and Regulatory as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the ESA action area. &nbsp;This delay resulted in a domino effect to subsequent milestones. &nbsp;Informal ESA consultation is anticipated with no change to final completion date until complete ESA submission is determined.</p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Non-conformance Explanation:
    Internal coordination among USACE 408 and Regulatory as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the ESA action area.  This delay resulted in a domino effect to subsequent milestones.  Informal ESA consultation is anticipated with no change to final completion date until complete ESA submission is determined.
Current Target Date:
Response Date