Santee Sioux Tribe Water Capacity and Infrastructure Improvements

PERMITTING DASHBOARD PROJECT POSTING DATE: JUNE 24, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/12/2027

2 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Water Resources

SECTOR
Water Resources

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Section 408

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

The Santee Sioux Tribe proposes the construction of a 31-mile, approximately 10-inch diameter water transmission line, along with necessary infrastructure, to deliver clean and reliable water to the Santee Sioux Nation located in Knox County, Nebraska. By constructing a 31-mile pipeline to interconnect the Santee system with that of Randall Community Water District and their existing surface water supply from Lake Francis Case in South Dakota, the Tribe will eliminate their water emergency and provide an opportunity for the next seven generations to continue to live on their lands provided under Executive Order in 1866.

USDA previously served as the facilitating agency for FAST-41.  In February 2026, USACE was deemed the lead agency. 

 

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete