Complete
The USFWS Nebraska Field Office was ahead of schedule in completing these milestones in coordination with USACE. The consultation was determined to be informal which facilitated a streamlined review., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-08-2026 07-08-2026 07-23-2026 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- 08-06-2026 Yes
ESA Consultation Concludes (Agency Action) 12-21-2026 12-21-2026 08-06-2026 Yes
Planned
USFWS received the BA from USACE on 7/23. The USFWS NE FO will work as quickly as possible to conduct a thorough review of the documents provided. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-08-2026 07-08-2026 07-23-2026 Yes
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- 08-24-2026 No
ESA Consultation Concludes (Agency Action) 12-21-2026 12-21-2026 --- No
Planned
Internal coordination among USACE 408 and Regulatory, as well as with the Project Sponsor, created a delay in a complete application which was necessary to identify the ESA action area.  This delay resulted in a domino effect to subsequent milestones.  Informal ESA consultation is anticipated.  FWS will update the final completion date to align with informal consultation once a complete ESA consultation submission is submitted to FWS., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-08-2026 07-08-2026 07-24-2026 No
FWS determines ESA Consultation Package is Complete - Informal (Agency Action) --- --- 08-24-2026 No
ESA Consultation Concludes (Agency Action) 12-21-2026 12-21-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 07-08-2026 07-08-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-08-2026 08-08-2026 --- No
ESA Consultation Concludes (Agency Action) 12-21-2026 12-21-2026 --- No