Agency Milestone Date of
10/23/2023for
Section 106 consultation concluded (Agency Action)has passed by 1 business days
Milestones:
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
Additional Milestones:
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
PROJECT WEBSITE: Equinor's Empire Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/11/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Equinor Wind proposes to construct and operate the Empire Wind Energy Project located in Lease Area OCS-A 0512, which covers approximately 79,350 acres (ac; 32,112 hectares [ha]) and is located approximately 14 statute miles (mi) (12 nautical miles [nm], 22 kilometers [km]) south of Long Island, New York and 19.5 mi (16.9 nm, 31.4 km) east of Long Branch, New Jersey. The project includes development of the lease area in two wind farms, known as Empire Wind 1 (EW 1) and Empire Wind 2 (EW 2). EW 1 and EW 2 will be electrically isolated and independent from each other. Empire Wind proposes to construct and operate up to 147 wind turbines and up to 2 offshore substations with 2 cable routes under the terms of the Renewable Energy Lease.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the EIS, COP, Section 106, ESA, EFH, Section 10/404 completion date on March 23, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the OCS Air Permit completion date on September 06, 2023. The Executive Director determination is posted here.
<style type="text/css"><!--td {border: 1px solid #cccccc;}br {mso-data-placement:same-cell;}-->
</style>
On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.</p>
There are no milestones to display.
There are no milestones to display.