Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-18-2021 06-18-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-18-2021 06-18-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-12-2023 10-23-2023 11-21-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-18-2021 06-18-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-18-2021 06-18-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-12-2023 10-23-2023 11-21-2023 No
In Progress
The Section 106 consultation process is delayed for two reasons. First, there have been multiple changes to the terrestrial area of potential effect (APE) for the Section 106 consultation. These changes are due, in part, to USACE requesting that the Project Sponsor make changes to several submarine cable route approaches and landfall sites to avoid sand borrow areas. The Project Sponsor’s ongoing revisions to its onshore facilities additionally contributed to the difficulty in identifying the APE for Section 106. Second, the Project Sponsor did not provide the Geographic Information System (GIS) and Portable Document Format (PDF) files for their preliminary terrestrial, marine, and visual APEs for the Project until mid-April 2022, which did not allow for sufficient review prior to the April 18, 2022, Section 106 kickoff meeting with consulting parties or for inclusion in the DEIS by the original DEIS publication date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-18-2021 06-18-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-18-2021 06-18-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-12-2023 10-23-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 06-18-2021 06-18-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 06-18-2021 06-18-2021 --- Yes
Section 106 consultation concluded (Agency Action) 06-12-2023 06-12-2023 --- No