FAST-41 Missed Date: Environmental Impact Statement (EIS)
Final Required Milestone Date of 03/17/2022 for Issuance of Lead Agency Record of Decision has passed by 5 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Transit Administration
Final Required Milestone Date of 03/17/2022 for Issuance of Lead Agency Record of Decision has passed by 5 business days
Final Required Milestone Date of 03/17/2022 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 03/17/2022 for Issuance of decision for permit/approval has passed by 5 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
California, CalTrans
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Final Required Milestone Date of 12/22/2021 for Conclusion of ESA Consultation has passed by 5 business days
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 12/26/2021 and extended to 12/26/2023