USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
BLM requests this extension of the final milestone dates to allow sufficient time for review and incorporation of new information into consultation documents and environmental reviews
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-02-2025 12-22-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 09-05-2025 04-10-2026 --- No
Issuance of a Final EA (Agency Action) 12-05-2025 12-11-2026 --- No
EA Process Concluded (Agency Action) 01-09-2026 01-15-2027 --- No
Planned
The BLM is awaiting reports (Biological, Cultural, and Water Supply Assessment) from the project sponsor.  The project sponsor is also set to resubmit an updated plan of development (POD), version 10, for review in February.  The project is anticipated to be extended by 29 days, which would give BLM adequate time to review the reports and POD.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-02-2025 06-27-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 09-05-2025 10-31-2025 --- No
Issuance of a Final EA (Agency Action) 12-05-2025 01-02-2026 --- No
EA Process Concluded (Agency Action) 01-09-2026 02-06-2026 --- No
Planned
The BLM is awaiting reports (Biological, Cultural, and Water Supply Assessment) from the project sponsor. The project sponsor is also set to resubmit an updated plan of development (POD), version 10, for review in February. The project is anticipated to be extended by 29 days, which would give BLM adequate time to review the reports and POD.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-02-2025 06-27-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 09-05-2025 09-30-2025 --- No
Issuance of a Final EA (Agency Action) 12-05-2025 01-02-2026 --- No
EA Process Concluded (Agency Action) 01-09-2026 02-06-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 03-02-2025 05-02-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 09-05-2025 09-05-2025 --- No
Issuance of a Final EA (Agency Action) 12-05-2025 12-05-2025 --- No
EA Process Concluded (Agency Action) 01-09-2026 01-09-2026 --- No