FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Colorado
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 11/12/2019 and extended to 05/23/2021
Triggered missed date from extending Conclusion of ESA Consultation within 30 days of its current target date which was 01/24/2020 and extended to 07/08/2021
Triggered missed date from extending NOAA Issues any EFH conservation recommendations within 30 days of its current target date which was 10/30/2019 and extended to 06/07/2021
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
Triggered missed date from extending Issuance of Lead Agency Record of Decision within 30 days of its current target date which was 01/24/2020 and extended to 10/20/2021
Triggered missed date from extending Final Verification/Permit Decision Rendered within 30 days of its current target date which was 04/24/2020 and extended to 01/18/2022
Triggered missed date from extending Final Verification/Permit Decision Rendered within 30 days of its current target date which was 04/24/2020 and extended to 01/18/2022
Final Required Milestone Date of 08/11/2020 for Conclusion of ESA Consultation has passed by 5 business days