Bureau of Land Management
FAST-41 Missed Date:Safe Drinking Water Act, Underground Injection Control (UIC): Issuance of final UIC permit decision
Agency Milestone Date of 07/06/2022 for Issuance of final UIC permit decision has passed by 1 business days
FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)
Agency Milestone Date of 06/13/2024 for Scoping (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/05/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/27/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
Description:
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/31/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management