Bureau of Land Management
FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Final decision/agency action (Agency Action)
Triggered missed date from extending Final decision/agency action (Agency Action) within 30 days of its current target date which was 01/07/2026 and extended to 07/07/2028
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/29/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Electricity Transmission
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of War
Department of the Interior, Bureau of Reclamation
Description:
FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)
Agency Milestone Date of 11/17/2025 for Completed application received (Agency Action) has passed by 1 business days