Bureau of Land Management
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/08/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
FAST-41 Missed Date:Right-of-Way Authorization (DOI-BLM): Completed application received (Agency Action)
Triggered missed date from extending Completed application received (Agency Action) within 30 days of its current target date which was 11/21/2025 and extended to 05/02/2026
FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)
Triggered missed date from extending Scoping (Agency Action) within 30 days of its current target date which was 11/21/2025 and extended to 01/19/2026