Permitting Action Modification History

In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-plan submittal coordination meeting (Applicant Action) 12-20-2022 12-20-2022 --- Yes
Initial Mine Plan of Operations received (Applicant Action) 03-26-2025 03-26-2025 --- Yes
Completeness determination for Mine Plan of Operations (Agency Action) 04-30-2025 04-30-2025 --- Yes
Revised Mine Plan of Operations received (Applicant Action) 10-02-2025 10-02-2025 --- Yes
Issuance of decision for Mine Plan of Operations (Agency Action) 04-09-2027 04-09-2027 --- No
Financial assurance received (Applicant Action) 04-09-2027 04-09-2027 --- No