USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
After review there are no longer any deficiencies and the APD/SUPO has been accepted as of 1/9/2026, ahead of 1/14/26 milestone date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 10-15-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-09-2026 --- Yes
Final decision/agency action (Agency Action) 04-30-2026 04-30-2026 --- No
Planned
Just to follow up on what was discussed today:   Currently, Sponsor submits package on December 15 (or earlier, if possible). If no deficiencies on the package (BLM and USFS), accept on December 22. If deficient, issue letters of deficiency on December 22. If resubmittal is needed, Sponsor to submit revisions by January 7. If resubmittal is needed, Final determination by January 14 (assuming no additional deficiencies) .   The dashboard milestones for the 3 actions (Special Use Permit, Surface Use Plan [USFS], and Surface Use Plan [BLM]) will be changed to Jan 14.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 10-15-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 01-14-2026 --- No
Final decision/agency action (Agency Action) 04-30-2026 04-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 10-15-2025 --- Yes
Application deemed complete (Agency Action) 12-22-2025 12-22-2025 --- No
Final decision/agency action (Agency Action) 04-30-2026 04-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2025 10-15-2025 --- No
Application deemed complete (Agency Action) 12-22-2025 12-22-2025 --- No
Final decision/agency action (Agency Action) 04-30-2026 04-30-2026 --- No