Information about project-related public meetings, public hearings, and public comment periods
Plans and Schedules for Public and Tribal Outreach
NEPA documentation on ePlanning: https://eplanning.blm.gov/Project-Home/?id=3D00EE85-E859-F111-BEC6-001DD804183B
Federal Register Notice Posted 05/29/2026: Notice of Intent to prepare an Environmental Impact Statement for the proposed DeLamar Mine Project - Owyhee County, Idaho
Activity | Date | Intended Audience | Responsible Entity |
| Public Scoping Mtg -Jordan Valley, OR | 6/9/2026 | Public/Interested Parties | BLM |
| Public Scoping Mtg – Marsing, ID | 6/11/2026 | Public/Interested Parties | BLM |
| Public Scoping Period | 5/29/2026 – 6/29/2026 | Public/Interested Parties | BLM |
| Section 106 Mtg | 3/6/2026 | SHPO | BLM |
| Section 106 Mtg | 11/14/2024 | Shoshone-Paiute Tribes of the Duck Valley Indian Reservation | BLM |
| Section 106 Mtg | 1/9/2025 | Shoshone-Paiute Tribes of the Duck Valley Indian Reservation | BLM |
| Section 106 Mtg | 1/22/2026 | Shoshone-Paiute Tribes of the Duck Valley Indian Reservation | BLM |
| Section 106 Mtg | 5/15/2025 | Fort McDermitt Paiute Shoshone Tribe | BLM |