Permitting Action Modification History
Modifications on 11/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial Mine Plan of Operations received (Applicant Action) | 10-19-2026 | 09-15-2026 | Yes |
| Completeness determination for Mine Plan of Operations (Agency Action) | 11-18-2026 | 11-03-2026 | Yes |
| Issuance of decision for Mine Plan of Operations (Agency Action) | 02-04-2028 | 02-04-2028 | No |
| Financial assurance received (Applicant Action) | 02-07-2028 | 02-07-2028 | No |
Modifications on 09/25/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial Mine Plan of Operations received (Applicant Action) | 10-19-2026 | 09-15-2026 | Yes |
| Completeness determination for Mine Plan of Operations (Agency Action) | 11-18-2026 | 11-18-2026 | No |
| Issuance of decision for Mine Plan of Operations (Agency Action) | 02-04-2028 | 02-04-2028 | No |
| Financial assurance received (Applicant Action) | 02-07-2028 | 02-07-2028 | No |
Modifications on 03/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Initial Mine Plan of Operations received (Applicant Action) | 10-19-2026 | 10-19-2026 | No |
| Completeness determination for Mine Plan of Operations (Agency Action) | 11-18-2026 | 11-18-2026 | No |
| Issuance of decision for Mine Plan of Operations (Agency Action) | 02-04-2028 | 02-04-2028 | No |
| Financial assurance received (Applicant Action) | 02-07-2028 | 02-07-2028 | No |