National Telecommunications and Information Administration
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/15/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Bureau of Land Management
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
National Telecommunications and Information Administration
Explains NTIA NEPA structure and requirements, which align with the implementing procedures of the First Responder Network Authority.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
05/14/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
LEAD AGENCY
Department of Commerce, National Telecommunications and Information Administration
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Army, US Army Corps of Engineers - Section 408
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Bureau of Indian Affairs
Department of War, US Army Corps of Engineers - Regulatory
Description:
National Telecommunications and Information Administration
Provides information on a wide range of environmental and historic preservation topics, including regulatory compliance and development of different types of analysis. The topics include environmental and historic preservation compliance process and requirements; National Historic Preservation Act Section 106 compliance; Endangered Species Act Section 7 consultation; Wetland regulatory authority; Environmental Assessments; Categorical Exclusions; and climate resiliency.
FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)
Agency Milestone Date of 08/31/2023 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days