Permitting Action Modification History

Complete
Final EA and FONSI concluded ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-08-2023 12-08-2023 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 07-12-2024 07-11-2024 --- Yes
Issuance of a Final EA (Agency Action) 08-30-2024 08-23-2024 --- Yes
EA Process Concluded (Agency Action) 08-30-2024 08-23-2024 --- Yes
In Progress
Draft EA was published for a public comment period one day ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-08-2023 12-08-2023 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 07-12-2024 07-11-2024 --- Yes
Issuance of a Final EA (Agency Action) 08-30-2024 08-30-2024 --- No
EA Process Concluded (Agency Action) 08-30-2024 08-30-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 12-08-2023 12-08-2023 --- Yes
Issuance of a Draft EA / Release for Public Review (Agency Action) 07-12-2024 07-12-2024 --- No
Issuance of a Final EA (Agency Action) 08-30-2024 08-30-2024 --- No
EA Process Concluded (Agency Action) 08-30-2024 08-30-2024 --- No