Non-Federal Hydropower Licenses

Project Name: Responsible Agency:
Federal Energy Regulatory Commission
Status:
Planned
POC Name:
Evan Williams
POC Title:
Project Manager

Description:

The Commission's issuance of a decision on a license application under the Federal Power Act is dependent on the issuance of a final National Environmental Policy Act document, the resolution of consultation under section 106 of the National Historic Preservation Act, and the issuance of a water quality certificate under section 401 of the Clean Water Act, if applicable.  The milestone target dates below are dependent on the project sponsor resolving all application deficiencies, additional information needs, and required studies by January 31, 2027.

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Current Target Date:
Final decision/agency action (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/21/2028
  • Section 106 Review : Section 106 consultation concluded (Agency Action)
    - Current Target Date: 10/19/2028
Current Target Date: