White Pine Pumped Storage

PERMITTING DASHBOARD PROJECT POSTING DATE: MARCH 13, 2023

PROJECT WEBSITE: https://www.whitepinepumpedstorage.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/30/2025

0 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The White Pine Pumped Storage Project (P-14851) is a proposed 1,000-megawatt (MW) closed-loop pumped storage hydroelectric power facility that would be located in White Pine County, NV.  Proposed new Project facilities, including the upper and lower reservoirs, underground water conveyance structures, underground powerhouse with generating and pumping equipment, groundwater supply wells, switchyard, access roads and tunnels, and ancillary facilities would be located approximately eight (8) miles northeast of the City of Ely.  The proposed new 345-kilovolt (kV) Project transmission line would extend approximately 25 miles west from the Project switchyard to the existing Robinson Summit substation located south of US-50.  The Project transmission line would be located predominantly on lands managed by the BLM within the 110-114 Corridor (Ely to Milford) of the Section 368 Region 3 Energy Corridor and immediately north of the existing NV Energy transmission line #3430 (BLM serial number 63162).  The Project would occupy 1,095.76 acres of federal land managed by the U.S. Bureau of Land Management.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete