USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Roberta Budnik
POC Title:
Project Manager
Action Outcome:
Permit issued/verified

Description:

The US Army Corps of Engineers Alaska District is reviewing an application for an individual standard permit pursuant to Section 404 of the Clean Water Act (CWA) and Section 10 of the Rivers and Harbors Act, which requires Department of Army authorization for the discharge of dredged and fill material, and work in “waters of the U.S.”  

In accordance with the Energy Policy Act, the Alaska District expects to render a permit decision within 90 days of FERC completing its FEIS.  This decision is dependent upon receiving documentation of compliance with Section 7 of the Endangered Species Act, Section 106 of the National Historic Preservation Act, and the Magnuson-Stevens Act (Essential Fish Habitat) from FERC.  This decision is also dependent upon receiving from the applicant a complete application, information on alternatives, and a mitigation plan as outlined in 33 CFR 332 at least 120 days prior to June 24, 2020.  The Corps also cannot issue a permit until the State of Alaska and the U.S. Environmental Protection Agency issue Section 401 Water Quality Certifications, or waive the requirement of such certifications.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Milestone Details

The applicant submitted an incomplete permit application on 14 April 2017.  The Corps requested additional information required to make the application complete on 16 June 2017.  The applicant submitted additional information for the permit application on 21 March 2018.  The Corps reviewed the additional information, and on 18 May 2018, requested additional information from the applicant to complete the application, including information on project impacts, mitigation (avoidance, minimization, and compensation), restoration, and revegetation.

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Milestone Details

The applicant submitted a revised application on November 8, 2019, and subsequently submitted addtional information to make the application complete on December 11, 2019.  The revised application reflects the applicant’s adoption of the Denali National Park and Preserve Alternative. 

Date completed:  12/11/2019

Publication of Public Notice (Agency Action)
Completed Date:
Milestone Details

The Corps published a Public Notice on December 30, 2019, with a 60-day comment period. 

Final Verification/Permit Decision Rendered (Agency Action)
Completed Date:
Milestone Details

The Alaska District signed their Record of Decision on June 24, 2020, finding that the issuance of a DA permit for the Project is consistent with National Policy, statutes, and administrative directives, and is not contrary to the public interest.