Description:
Endangered Species Act Section 7 Consultation.
Final Completion Date: 135 days* following the Consultation Initiation Date.
*The final completion date is contingent upon NMFS receiving sufficient information to initiate formal ESA consultation.
Milestones:
Target: Anticipated concurrent with issuance of FERC’s Draft EIS. *This target timeline is dependent on a consultation request from FERC, consisting of a final Biological Assessment, concurrent with the draft NEPA document.
Target completion is 30 days after issuance of draft EIS and receipt of Biological Assessment. *This consultation initiation target timeline is dependent upon NMFS receiving sufficient information (complete final Biological Assessment) to initiate formal ESA consultation.
Target: 135 days* following the Consultation Initiation Date. *The final completion date is contingent upon NMFS receiving sufficient information to initiate formal ESA consultation.