Final Required Milestone Date of 05/30/2022 for Section 106 consultation concluded has passed by 5 business days
Cooperating under NEPA
Participating
California
Description:
This milestone will be paused until the proponent submits an updated Cultural survey report, biological assessment, project description and proposed action. These items were to be submitted no later than October 2019. We anticipate receiving these components between mid- January 2020 and March 2020.
**Update January 8, 2021: Milestone will remain on pause until a final report is submitted.
Milestones:
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Current Target Date: 03/25/2022
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Current Target Date: 03/25/2022
PROJECT WEBSITE: Replacement of Lines 901 and 903
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Pipelines
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
Plains Pipeline, L.P. filed a right-of-way application with the Bureau of Land Management (BLM) Bakersfield Office on January 9, 2018, for the replacement and abandonment of existing oil pipelines 901 and 903. The project spans multiple local, State and Federal jurisdictions. The proposed project consists of installation and operation of approximately 123.4 miles of replacement pipelines 901R and 903R, supporting access roads, valves, and pump stations.
The project was paused from November 1, 2019 to January 4, 2021. Plains Pipeline, L.P. submitted an updated project description and supporting documents during this time. A Standard Individual Permit (SIP) application was submitted to the United States Army Corps of Engineers on October 5, 2020 to replace the original Nation Wide Permit (NWP) 12 Per-Construction Notification(PCN) application while the project was in paused status.
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
- Current Target Date: 03/25/2022