Permitting Action Modification History
Modifications on 10/25/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 08-14-2018 | 08-14-2018 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 05-13-2021 | 05-30-2022 | --- | No |
Modifications on 04/12/2022
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 08-14-2018 | 08-14-2018 | --- | Yes |
| Section 106 consultation concluded (Agency Action) | 05-13-2021 | 05-30-2022 | --- | No |