USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Plains Pipeline, L.P. Lines 901 and 903 Replacement Project

PERMITTING DASHBOARD PROJECT POSTING DATE: AUGUST 07, 2018

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

1 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Description:

Plains Pipeline, L.P. filed a right-of-way application with the Bureau of Land Management (BLM) Bakersfield Office on January 9, 2018, for the replacement and abandonment of existing oil pipelines 901 and 903. The project spans multiple local, State and Federal jurisdictions. The proposed project consists of installation and operation of approximately 123.4 miles of replacement pipelines 901R and 903R, supporting access roads, valves, and pump stations. 

The project was paused from November 1, 2019 to January 4, 2021. Plains Pipeline, L.P. submitted an updated project description and supporting documents during this time. A Standard Individual Permit (SIP) application was submitted to the United States Army Corps of Engineers on October 5, 2020 to replace the original Nation Wide Permit (NWP) 12 Per-Construction Notification(PCN) application while the project was in paused status.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete