USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by Anonymous on

Final Required Milestone Date of 03/09/2021 for Final Verification/Permit Decision Rendered has passed by 5 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Tyler Krug
POC Title:
Project Manager

Description:

The Portland District is reviewing a Department of the Army individual permit application pursuant to Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act for the construction of structures and work in navigable waters of the U.S. and the discharge of dredged or fill material into waters of the U.S., including wetlands, respectively.  The review is associated with the construction of a liquefied natural gas export terminal, pipeline, and appurtenant features. This work is associated with Jordan Cove LNG Terminal and Pacific Connector Gas Pipeline Project.

On 18 Nov 2020, USACE moved this action to “paused” status until such time our agency receives either a decision on or a date for a decision on the Section 401 Water Quality Certification/waiver.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Publication of Public Notice (Agency Action)
Completed Date:
Milestone Details

Pre-Construction Notification (PCN) / Application Deemed Complete on 08 May 2018 Public Notice issued and complete on 22 May 2018

 

Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development; the receipt of a Section 401 Water Quality Certification from the Oregon Department of Environmental Quality or a determination a waiver of the certification has occurred; and a Section 408 compliance determination from the Corps Portland District Planning, Programs, and Project Management Division.  Finally, we require a complete application, a complete mitigation plan, and information regarding alternatives from the applicant prior to rendering a permit decision.  Should submittal of any required information be delayed, the Corps will adjust its timeline accordingly.  If the information above is not received from FERC, state or Federal agencies, and/or the non-Federal applicant at least 60 days prior to the 90 day deadline, the Corps will consider this delay and adjust the decision deadline to allow a 60 day review once all required documentation/information is received.  The Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable. 

On 18 Nov 2020, USACE moved this action to “paused” status until such time our agency receives either a decision on or a date for a decision on the Section 401 Water Quality Certification/waiver.

 

 

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development; the receipt of a Section 401 Water Quality Certification from the Oregon Department of Environmental Quality or a determination a waiver of the certification has occurred; and a Section 408 compliance determination from the Corps Portland District Planning, Programs, and Project Management Division.  Finally, we require a complete application, a complete mitigation plan, and information regarding alternatives from the applicant prior to rendering a permit decision.  Should submittal of any required information be delayed, the Corps will adjust its timeline accordingly.  If the information above is not received from FERC, state or Federal agencies, and/or the non-Federal applicant at least 60 days prior to the 90 day deadline, the Corps will consider this delay and adjust the decision deadline to allow a 60 day review once all required documentation/information is received.  The Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable. 

On 18 Nov 2020, USACE moved this action to “paused” status until such time our agency receives either a decision on or a date for a decision on the Section 401 Water Quality Certification/waiver.

 

 

Project

PROJECT WEBSITE: Jordan Cove LNG

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2020

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Jordan Cove LNG Project (Docket No. CP17-495-000) includes the construction and operation of a liquefied natural gas (LNG) export terminal on the North Spit of Coos Bay in Coos County, Oregon.  The terminal would include gas inlet facilities, a metering station, a gas conditioning plant, five liquefaction trains and associated equipment, two full-containment LNG storage tanks, an LNG transfer line, LNG ship loading facilities, a marine slip, a marine offloading facility, a new access channel between the Coos Bay Navigation Channel and the new marine slip, and enhancements to the existing Coos Bay Navigation Channel at four turns.  In addition, the terminal would include emergency and hazard, electrical, security, control, and support systems, administrative buildings, and a temporary workforce housing facility.  The LNG terminal would be designed to liquefy about 1.04 billion cubic feet per day of LNG for export to markets across the Pacific Rim.

The Pacific Connector Gas Pipeline (Docket No. CP-17-494) includes the construction and operation an approximately 229-mile-long, 36-inch-diameter interstate natural gas transmission pipeline and associated aboveground facilities.  The pipeline would originate near Malin in Klamath County, Oregon, traverse Douglas and Jackson Counties, and terminate (at the LNG Terminal) in Coos County, Oregon.  The pipeline would be capable of transporting about 1.2 billion cubic feet per day of natural gas.  The associated aboveground facilities would include the new Klamath Compressor Station (61,500 horsepower) near Malin, Oregon; 3 new meter stations; 5 new pig launchers and receivers; 17 mainline block valves; and a gas control communication system.

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Jordan Cove LNG Project.  

Additional Federal Agency Authorization Timetable for the Jordan Cove LNG and Pacific Connector Gas Pipeline Project
Agency Permit Status Applicable Timelines
U.S. Coast Guard Letter of Recommendation Completed Receipt of Letter of Intent:  April 2006
Receipt of Water Suitability Assessment:  10/1/17
Letter of Recommendation to FERC:  5/10/18  

 

Last updated January 7, 2021

field_status
System Comments
Final Required Milestone Date of 03/09/2021 for Final Verification/Permit Decision Rendered has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The final milestone target date is dependent on the receipt of compliance documentation regarding Tribal Trust Responsibilities, Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act, and Essential Fish Habitat compliance pursuant to the Magnuson-Stevens Fishery Conservation and Management Act from FERC; the receipt of a Coastal Zone Management Act concurrence determination or presumed concurrence determination from the Oregon Department of Land Conservation and Development; the receipt of a Section 401 Water Quality Certification from the Oregon Department of Environmental Quality or a determination a waiver of the certification has occurred; and a Section 408 compliance determination from the Corps Portland District Planning, Programs, and Project Management Division.  Finally, we require a complete application, a complete mitigation plan, and information regarding alternatives from the applicant prior to rendering a permit decision.  Should submittal of any required information be delayed, the Corps will adjust its timeline accordingly.  If the information above is not received from FERC, state or Federal agencies, and/or the non-Federal applicant at least 60 days prior to the 90 day deadline, the Corps will consider this delay and adjust the decision deadline to allow a 60 day review once all required documentation/information is received.  The Corps will continue its evaluation concurrent with the federal environmental review process as much as practicable. 

On 18 Nov 2020, USACE moved this action to “paused” status until such time our agency receives either a decision on or a date for a decision on the Section 401 Water Quality Certification/waiver.