Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-18-2024 03-18-2024 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-18-2024 03-18-2024 --- Yes
Section 106 consultation concluded (Agency Action) 05-20-2026 10-14-2026 --- No
In Progress
Section 106 consultation is being conducted through the Section 106 NEPA substitution process and is interrelated with the NEPA timeline which is being updated so the Section 106 date was changed accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-18-2024 03-18-2024 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-18-2024 03-18-2024 --- Yes
Section 106 consultation concluded (Agency Action) 05-20-2026 10-14-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-18-2024 03-18-2024 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-18-2024 03-18-2024 --- Yes
Section 106 consultation concluded (Agency Action) 05-20-2026 05-20-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-18-2024 03-18-2024 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-18-2024 03-18-2024 --- No
Section 106 consultation concluded (Agency Action) 05-20-2026 05-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 03-18-2024 03-18-2024 --- No
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 03-18-2024 03-18-2024 --- No
Section 106 consultation concluded (Agency Action) 05-20-2026 05-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) --- --- --- No
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) --- --- --- No
Section 106 consultation concluded (Agency Action) --- --- --- No