The Section 106 consultation process is delayed for two reasons. First, there have been multiple changes to the terrestrial area of potential effect (APE) for the Section 106 consultation. These changes are due, in part, to USACE requesting that the Project Sponsor make changes to several submarine cable route approaches and landfall sites to avoid sand borrow areas. The Project Sponsor’s ongoing revisions to its onshore facilities additionally contributed to the difficulty in identifying the APE for Section 106. Second, the Project Sponsor did not provide the Geographic Information System (GIS) and Portable Document Format (PDF) files for their preliminary terrestrial, marine, and visual APEs for the Project until mid-April 2022, which did not allow for sufficient review prior to the April 18, 2022, Section 106 kickoff meeting with consulting parties or for inclusion in the DEIS by the original DEIS publication date.
Milestones:
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
Additional Milestones:
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
PROJECT WEBSITE: Equinor's Empire Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/11/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Army, US Army Corps of Engineers - Regulatory
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Equinor Wind proposes to construct and operate the Empire Wind Energy Project located in Lease Area OCS-A 0512, which covers approximately 79,350 acres (ac; 32,112 hectares [ha]) and is located approximately 14 statute miles (mi) (12 nautical miles [nm], 22 kilometers [km]) south of Long Island, New York and 19.5 mi (16.9 nm, 31.4 km) east of Long Branch, New Jersey.
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
-
Monthly Status Report for November 2023:On track to meet the alternative completion date of Nov 21. BOEM is awaiting final signature on MOA.
-
Monthly Status Report for October 2023:On track to meet alternative completion date of Nov 21, 2023.
-
Non-conformance Explanation:BOEM is utilizing the NEPA substitution process to conduct the consultation, which aligns the consultation schedule with the NEPA process. BOEM determined the need to move the Section 106 milestone during the lockout period to align it with a new ROD milestone target. The additional time also allowed BOEM to honor a request by Consulting parties, including the Advisory Council on History Preservation and several tribes, for additional time to review the proposed mitigations due to their extensive nature.
Original Target Date: 06/12/2023
Milestone: Section 106 consultation concluded (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Section 106 consultation concluded (Agency Action) extended by 133
From: 06/12/2023
To: 10/23/2023