Milestone Extension: Section 106 Review

Submitted by danny.wiegand@… on

The Port of Corpus Christi Port Authority (PCCA) is the applicant for Department of the Army permits for the proposed Channel Deepening Project (CDP), which is located near Port Aransas, Nueces and Aransas Counties, Texas. PCCA proposes to deepen the existing Corpus Christi Ship Channel from the currently authorized depth of -54 feet to -77 feet and extend the existing offshore channel limits an additional 29,000 feet into the Gulf of Mexico. Specifically, PCCA’s proposed channel alignment would be within the existing channel bottom of the Corpus Christi Ship Channel, starting near the southeast side of Harbor Island, traversing easterly through Aransas Pass, and extending beyond the current Congressionally authorized terminus into the Gulf of Mexico. The proposed channel deepening would span approximately 13.8 miles and generate approximately 47 million cubic yards of dredge material. PCCA has proposed to use suitable dredged material for beneficial use by constructing nearshore berms and beach nourishment on San Jose and Mustang Islands, as well as to restore eroded shorelines impacted by Hurricane Harvey on Harbor Island and near the Port Aransas Nature Preserve. PCCA proposes to place dredged material determined not to be suitable for beneficial use in the Corpus Christi New Work Ocean Dredge Material Disposal Site, located offshore of Corpus Christi.

The Corps initiated Section 106 Consultation on May 18, 2022, through submittal of the results of the Terrestrial Cultural Resources Report to the SHPO. However, the SHPO and the Corps will not be able to conclude the 106 consultations for the entire project until the necessary marine archaeological surveys are completed by the applicant.

Unusual spring weather, larger sea states, and vessel availability issues have prevented the survey crew from conducting their work delaying the Marine Survey submission for several months.  The Corps received the surveys from the applicant on 26 August 2022. Upon review, the Corps has determined that the marine survey does not include surveys for modifications made to the project site.

In October 2021, the applicant modified the proposed project by relocating 9 nearshore berms. This relocation was made to address capacity issues in the original berms identified by the Corps modeling analysis. The Corps notified the applicant and recommended new locations based on the modeling. The applicant agreed to the new recommended relocation of the berms and modified their project. The modified berms were included in the June 2022 DEIS.

However, despite the Corps and applicant conducting biweekly status meetings on the CDP environmental review process, this change in location of the nearshore berms and the subsequent revision in the survey scope necessary to accurately complete the marine surveys was not captured, and thus the modified locations of the berms were not surveyed.  As such, the applicant still needs to survey the modified berm areas.

The current target date for the Section 106 Consultation Concluded Milestone is 18 October 2022.  Based on the need for the applicant to conduct additional marine surveys, the Corps, as the lead federal agency, is requesting to change the Section 106 Consultation Concluded Milestone target date to 10 February 2023.  This change is supported by the cooperating agencies, Galveston District leadership, and the project sponsor, PCCA. The Corps CERPO has been informed and does not object to the change. 

The extension of the Section 106 Consultation Concluded Milestone date from 18 October 2022 to 10 February 2023, will not affect any other milestone target dates in the permitting timetable.  The other permitting timetable milestones currently remain on track as scheduled.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Status:
In Progress
SHPO:

Texas

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for April 2023:
    The USACE has reviewed a revised draft report (submitted by CCSC on March 31). The USACE reviewed the draft report and requested additional revisions (April 7). The applicant addressed the comments and resubmitted the revised draft report (April 11). The USACE accepted the revisions and submitted the revised report along with their determinations to the SHPO for review and concurrence (April 14). The USACE instructed the applicant to submit a copy of the revised draft report to the Texas Historic Commission pursuant to state regulations. The SHPO will need to respond to the USACE's determinations no later than May 15.
  • Monthly Status Report for March 2023:
    The November 2022 marine archeological survey report was transmitted to the Texas Historical Commission (THC) by the Corps on November 18, 2022. The THC requested significant revisions by letter dated January 10, 2023. The PCCA’s consultant proposed to provide the revision by January 12, 2023, but did not submit them until January 27, 2023. The Corps completed their review and requested concurrence with the re-written report on January 30, 2023. The THC concluded in their February 9, 2023, letter that: “there have been consistent issues with the processing and presentation of the contoured magnetic data in the original and revised draft reports submitted to the THC in December 2022 and January 2023. These irregularities affect how specific interpretative models are applied for identifying potential shipwreck targets.” Subsequently, PCCA’s contractor re-submitted a preliminary revised report to the THC on February 15, 2023 to which the THC responded the same day stating, “This data is actually more problematic and less acceptable than the previous versions.” Based upon the facts above the Corps recommended and FPISC accepted the milestone recovery date of  12JUL2023.   On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Monthly Status Report for February 2023:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Non-conformance Explanation:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  Alterative Completion Date: 07/12/2023
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for April 2023:
    The USACE has reviewed a revised draft report (submitted by CCSC on March 31). The USACE reviewed the draft report and requested additional revisions (April 7). The applicant addressed the comments and resubmitted the revised draft report (April 11). The USACE accepted the revisions and submitted the revised report along with their determinations to the SHPO for review and concurrence (April 14). The USACE instructed the applicant to submit a copy of the revised draft report to the Texas Historic Commission pursuant to state regulations. The SHPO will need to respond to the USACE's determinations no later than May 15.
  • Monthly Status Report for March 2023:
    The November 2022 marine archeological survey report was transmitted to the Texas Historical Commission (THC) by the Corps on November 18, 2022. The THC requested significant revisions by letter dated January 10, 2023. The PCCA’s consultant proposed to provide the revision by January 12, 2023, but did not submit them until January 27, 2023. The Corps completed their review and requested concurrence with the re-written report on January 30, 2023. The THC concluded in their February 9, 2023, letter that: “there have been consistent issues with the processing and presentation of the contoured magnetic data in the original and revised draft reports submitted to the THC in December 2022 and January 2023. These irregularities affect how specific interpretative models are applied for identifying potential shipwreck targets.” Subsequently, PCCA’s contractor re-submitted a preliminary revised report to the THC on February 15, 2023 to which the THC responded the same day stating, “This data is actually more problematic and less acceptable than the previous versions.” Based upon the facts above the Corps recommended and FPISC accepted the milestone recovery date of  12JUL2023.   On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Monthly Status Report for February 2023:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Non-conformance Explanation:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  Alterative Completion Date: 07/12/2023
Current Target Date:
Project

PROJECT WEBSITE: USACE website for the Port of Corpus Christi Authority Channel Deepening EIS Pr…

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2024

7 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Ports and Waterways

SECTOR
Ports and Waterways

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The purpose of the proposed project is to construct a channel with the capability to accommodate the transit of fully laden Very Large Crude Carriers (VLCCs) from multiple locations on Harbor Island, TX and into the Gulf of Mexico. The Department of the Army permit application submitted by the project sponsor to USACE, the FAST-41 Initiation Notice, public notices, and other significant supporting documents for the environmental review process can be found on the USACE Galveston District website at: https://www.swg.usace.army.mil/Missions/Regulatory/Special-Projects-Environmental-Impact-Statements/.  Additional information on the EIS process and public involvement, including information on public meetings, can also be found on USACE's website at: https://pccaeisproject.com/.

Update: 

The Executive Director granted a U.S. Army Corps of Engineers request to extend the Section 106 Review completion date. The Executive Director determination is posted here.

field_status
System Comments
Furthest out
Original Target Date: 02/04/2021
Milestone: Section 106 consultation concluded (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Section 106 consultation concluded (Agency Action) extended by 736
From: 10/18/2022
To: 02/10/2023
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for April 2023:
    The USACE has reviewed a revised draft report (submitted by CCSC on March 31). The USACE reviewed the draft report and requested additional revisions (April 7). The applicant addressed the comments and resubmitted the revised draft report (April 11). The USACE accepted the revisions and submitted the revised report along with their determinations to the SHPO for review and concurrence (April 14). The USACE instructed the applicant to submit a copy of the revised draft report to the Texas Historic Commission pursuant to state regulations. The SHPO will need to respond to the USACE's determinations no later than May 15.
  • Monthly Status Report for March 2023:
    The November 2022 marine archeological survey report was transmitted to the Texas Historical Commission (THC) by the Corps on November 18, 2022. The THC requested significant revisions by letter dated January 10, 2023. The PCCA’s consultant proposed to provide the revision by January 12, 2023, but did not submit them until January 27, 2023. The Corps completed their review and requested concurrence with the re-written report on January 30, 2023. The THC concluded in their February 9, 2023, letter that: “there have been consistent issues with the processing and presentation of the contoured magnetic data in the original and revised draft reports submitted to the THC in December 2022 and January 2023. These irregularities affect how specific interpretative models are applied for identifying potential shipwreck targets.” Subsequently, PCCA’s contractor re-submitted a preliminary revised report to the THC on February 15, 2023 to which the THC responded the same day stating, “This data is actually more problematic and less acceptable than the previous versions.” Based upon the facts above the Corps recommended and FPISC accepted the milestone recovery date of  12JUL2023.   On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Monthly Status Report for February 2023:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Non-conformance Explanation:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  Alterative Completion Date: 07/12/2023
Current Target Date:
Furthest Original Target Date Milestone
Section 106 consultation concluded (Agency Action)
  • Monthly Status Report for April 2023:
    The USACE has reviewed a revised draft report (submitted by CCSC on March 31). The USACE reviewed the draft report and requested additional revisions (April 7). The applicant addressed the comments and resubmitted the revised draft report (April 11). The USACE accepted the revisions and submitted the revised report along with their determinations to the SHPO for review and concurrence (April 14). The USACE instructed the applicant to submit a copy of the revised draft report to the Texas Historic Commission pursuant to state regulations. The SHPO will need to respond to the USACE's determinations no later than May 15.
  • Monthly Status Report for March 2023:
    The November 2022 marine archeological survey report was transmitted to the Texas Historical Commission (THC) by the Corps on November 18, 2022. The THC requested significant revisions by letter dated January 10, 2023. The PCCA’s consultant proposed to provide the revision by January 12, 2023, but did not submit them until January 27, 2023. The Corps completed their review and requested concurrence with the re-written report on January 30, 2023. The THC concluded in their February 9, 2023, letter that: “there have been consistent issues with the processing and presentation of the contoured magnetic data in the original and revised draft reports submitted to the THC in December 2022 and January 2023. These irregularities affect how specific interpretative models are applied for identifying potential shipwreck targets.” Subsequently, PCCA’s contractor re-submitted a preliminary revised report to the THC on February 15, 2023 to which the THC responded the same day stating, “This data is actually more problematic and less acceptable than the previous versions.” Based upon the facts above the Corps recommended and FPISC accepted the milestone recovery date of  12JUL2023.   On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Monthly Status Report for February 2023:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.       
  • Non-conformance Explanation:
    The USACE is revising the target date for the final Milestone of the Section 106 review to July 12, 2023 to allow time for the project applicant to address SHPO objections and recommendations for the marine archeological survey report and allow time for the USACE and SHPO to complete Section 106 consultation. The milestone for Section 106 consultation concluded has been previously re-scheduled twice in 2022. During early 2022, the project applicant’s marine archaeological surveys were delayed by unusual spring weather, larger sea states, and vessel availability issues. The Milestone was rescheduled from June 10, 2022 to October 18, 2022. The project applicant submitted the initial marine archeological survey report in August 2022 but the USACE determined outdated project features had been surveyed and surveys of recently proposed project features were required. The Milestone was rescheduled to February 10, 2023. The completed marine archeological survey report was submitted November 2022 and has undergone multiple revisions with substantive objections and recommendations from the SHPO documented in letters dated January 10, 2023 and February 9, 2023. The project applicant’s consultant has concluded the survey data will require reprocessing. The project applicant needs time to reprocess this data and develop a report.  The USACE and SHPO have concluded that an iterative, concurrent review of the report with the project applicant and their consultant will conclude July 12, 2023.  Alterative Completion Date: 07/12/2023
Current Target Date: