Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-04-2021 05-18-2022 --- Yes
Section 106 consultation concluded (Agency Action) 02-04-2021 02-10-2023 05-15-2023 Yes
Complete
On 15MAY2023, we concluded the consultation process with the SHPO for Section 106.  This was a milestone USACE slipped on 10FEB2023 due to the applicant providing an insufficient marine archeologic analysis for their report and the milestone was place in non-conformance by FPISC.  USACE SWG, Texas SHPO, and the Applicant provided a recovery target date of 12JUL2023 anticipating numerous revisions and formal submissions; however, due to creative informal coordination between SWG and SHPO the concerns regarding insufficient analysis were promptly addressed allowing for a single formal submission resulting in an expedited milestone completion.        , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-04-2021 05-18-2022 --- Yes
Section 106 consultation concluded (Agency Action) 02-04-2021 02-10-2023 --- Yes
In Progress
Incomplete 106 survey information received from the applicant (survey information did not capture change in project feeder berm areas).  Additional survey work required in the berm areas, requiring a milestone date change. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-04-2021 05-18-2022 --- Yes
Section 106 consultation concluded (Agency Action) 02-04-2021 02-10-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-18-2022 05-18-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-20-2022 10-18-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 05-18-2022 05-18-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-20-2022 07-20-2022 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) --- 05-18-2022 --- No
Section 106 consultation concluded (Agency Action) --- 07-20-2022 --- No