The explanation for the milestone date change was outlined in the Executive Director Determination request submitted to the Permitting Council on Sep 21, 2026.
Milestones:
-
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 09/24/2026
-
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 09/24/2026
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/29/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
High-performance computing and advanced computer hardware and software
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Description:
The data center complex will be located on approximately 1,300 acres of private land adjacent to the Department of Energy Portsmouth Site in Pike County, Ohio. The project consists of two data center buildings and their associated infrastructure, including access roads, administrative buildings, substations, laydown yards, and parking infrastructure.
The Executive Director granted a U.S. Army Corps of Engineers request to extend completion dates for the environmental assessment and the permit decision under Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act on September 28, 2026. The Executive Director Determination is posted here.
-
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 09/24/2026
-
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 09/24/2026
Original Target Date: 12/23/2026
Milestone: Final Verification/Permit Decision Rendered (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered (Agency Action) extended by 37
From: 12/23/2026
To: 01/29/2027