Permitting Action Modification History
Modifications on 09/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 05-27-2026 | 05-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-10-2026 | 07-10-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 07-13-2026 | 07-13-2026 | --- | Yes |
| Provisional Notification (Agency Action) | 10-01-2026 | 11-30-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 12-23-2026 | 01-29-2027 | --- | No |
Modifications on 08/27/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 05-27-2026 | 05-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-10-2026 | 07-10-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 07-13-2026 | 07-13-2026 | --- | Yes |
| Provisional Notification (Agency Action) | 10-01-2026 | 10-30-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 12-23-2026 | 12-23-2026 | --- | No |
Modifications on 08/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) | 05-27-2026 | 05-27-2026 | --- | Yes |
| Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) | 07-10-2026 | 07-10-2026 | --- | Yes |
| Publication of Public Notice (Agency Action) | 07-13-2026 | 07-13-2026 | --- | Yes |
| Provisional Notification (Agency Action) | 10-01-2026 | 10-01-2026 | --- | No |
| Final Verification/Permit Decision Rendered (Agency Action) | 12-23-2026 | 12-23-2026 | --- | No |