PORTS Technology Campus

PERMITTING DASHBOARD PROJECT POSTING DATE: JUNE 11, 2026

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/29/2027

2 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

High-performance computing and advanced computer hardware and software

SECTOR
High-performance computing and advanced computer hardware and software

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The data center complex will be located on approximately 1,300 acres of private land adjacent to the Department of Energy Portsmouth Site in Pike County, Ohio. The project consists of two data center buildings and their associated infrastructure, including access roads, administrative buildings, substations, laydown yards, and parking infrastructure.

The Executive Director granted a U.S. Army Corps of Engineers request to extend completion dates for the environmental assessment and the permit decision under Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act on September 28, 2026.  The Executive Director Determination is posted here.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete