Milestone Extension: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act

Submitted by craig.litteken… on

Based upon the 29 July 2022 initiation of formal consultation, the Biological Opinion (BO) was anticipated by 12 December 2022.  On 12 December 2022 the USFWS and the FERC agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information important to the supplemental Biological Assessment. Furthermore, on 6 December 2022, the applicant provided revised information related to Clean Water Act Section 404 discharges.  On 12 December 2022, the Corps responded with the issuance of a supplemental public notice (available by clicking on the link below). 

https://www.lrh.usace.army.mil/Missions/Regulatory/Public-Notices/Article/3243440/lrh-2015-00592-gbr-lrp-2015-798-nao-2015-0898/

The Corps has projected the need for a minimum of 60 days to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.  The 60-day timeframe is also the minimum necessary to evaluate the need for further milestone extension requests should the contents of the final BO trigger additional unforeseen analysis and timeframes.  Therefore, as a cooperating agency, the Corps has requested a 60 day extension of the Final Decision Milestone target date from 17 February 2023 to 18 April 2023.  FERC has consulted with the Corps and the project sponsor regarding this milestone extension.

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Status:
In Progress
POC Name:
Mr. Adam Fannin
POC Title:
Regulatory Project Manager, USACE, Regulatory Division, Huntington District Energy Resource Branch

Description:

Section 10 Rivers and Harbors Act/Section 404 Clean Water Act:  The Secretary of the Army, acting through the U.S. Army Corps of Engineers (Corps), has authority to permit the discharge of dredged or fill material in waters of the U.S. under Section 404 of the Clean Water Act (CWA). The Corps also has authority to permit work and the placement of structures in navigable waters of the U.S. under Sections 9 and 10 of the Rivers and Harbors Act of 1899 (RHA) (see 33 CFR 320.2).

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Publication of Public Notice (Agency Action)
Completed Date:
Final Verification/Permit Decision Rendered (Agency Action)
  • Monthly Status Report for May 2023:
    USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice.  USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.  USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
  • Monthly Status Report for April 2023:
    USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.    USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
  • Monthly Status Report for March 2023:
    The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
  • Non-conformance Explanation:
    The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
Current Target Date:
Milestone
Final Verification/Permit Decision Rendered (Agency Action)
  • Monthly Status Report for May 2023:
    USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice.  USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.  USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
  • Monthly Status Report for April 2023:
    USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.    USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
  • Monthly Status Report for March 2023:
    The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
  • Non-conformance Explanation:
    The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
Current Target Date:
Project

PROJECT WEBSITE: https://www.mountainvalleypipeline.info/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/23/2023

21 out of 21

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, National Park Service

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of Agriculture

Department of Agriculture, US Forest Service

Description:

On August 18, 2022, Mountain Valley Pipeline, LLC submitted a FAST-41 Initiation Notice for the outstanding federal environmental reviews and authorizations for the project following associated court decisions. A determination of FAST-41 coverage was made on September 1, 2022. 

The project was previously in the initial inventory of FAST-41 covered projects designated by the Executive Director of the Federal Permitting Improvement Steering Council in September 2016 before being closed out on the Permitting Dashboard in late 2017.  

As described in the project sponsor’s FAST-41 Initiation Notice, the project includes the construction of approximately 304 miles of natural gas pipeline in West Virginia and Virginia, three new compressor stations in West Virginia, metering stations, taps, and appurtenant facilities. The project would provide up to 2,000,000 dekatherms per day of firm natural gas transportation service from northern West Virginia to southwestern Virginia.

Last updated on October 31, 2022.

field_status
System Comments
Furthest out
Original Target Date: 02/17/2023
Milestone: Final Verification/Permit Decision Rendered (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final Verification/Permit Decision Rendered (Agency Action) extended by 60
From: 02/17/2023
To: 04/18/2023
Approver Comments
This milestone was originally in ED review, but the ED determination was not signed prior to the 30-day lockout. Therefore, the action is no longer subject to ED review, but instead, the action will be in nonconformance. USACE confirmed on 2/21/23 that they did not meet their 2/17/23 final milestone. The ED review that currently shows on the backside of the dashboard needs to be rejected to allow the dashboard to trigger the nonconformance. Within 5-days of the enabling the nonconformance, the final USACE milestone will be updated with the appropriate nonconformance explanation and alternative completion date.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final Verification/Permit Decision Rendered (Agency Action)
  • Monthly Status Report for May 2023:
    USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice.  USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.  USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
  • Monthly Status Report for April 2023:
    USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.    USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
  • Monthly Status Report for March 2023:
    The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
  • Non-conformance Explanation:
    The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
Current Target Date:
Furthest Original Target Date Milestone
Final Verification/Permit Decision Rendered (Agency Action)
  • Monthly Status Report for May 2023:
    USACE continues to review the information provided in the Biological Opinion (BO) and comments received from the public notice.  USACE final decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.  USACE is awaiting the 401 water quality certification , before making a final permit decision under Section 404 of the Clean water Act and Section 10 of the Rivers and Harbors Act of 1899, and anticipate making these decisions by the current milestone reflected on the dashboard of June 30, 2023.
  • Monthly Status Report for April 2023:
    USACE continues to review the information provided in the revised BO and comments received from the most recent public notice. USACE final permit decision under Section 404 of the Clean Water Act is dependent on the WVDEP 401 Water Quality Certification.    USACE is awaiting the 401 water quality certification, before rendering a final permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (CWA).
  • Monthly Status Report for March 2023:
    The USACE permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   The FWS revised BO was issued on February 28, 2023. USACE has identified an alternative completion date of April 29, 2023, for their final Section 10/404 permit decision.
  • Non-conformance Explanation:
    The U.S. Army Corps of Engineer’s (USACE’s) permit decision under Section 10 of the Rivers and Harbors Act of 1899 and Section 404 of the Clean Water Act (the “Section 10/404 final completion date) is dependent upon the Federal Energy Regulatory Commission’s (FERC’s) completion of consultation with the Department of the Interior, Fish and Wildlife Service (FWS) under the Endangered Species Act (ESA). When issuing a Section 10/404 permit, USACE considers any Biological Opinion (BO) and mitigation measures resulting from ESA consultation to ensure the final Section 10/404 permit decision is consistent with the analysis and requirements of the BO. Conclusion of ESA consultation was originally anticipated to be December 12, 2022, but FERC and FWS agreed to extend the formal consultation period by 60 days to allow for additional time to coordinate and review information. USACE projected the need for a minimum of 60 days after issuance of the BO to review the final BO, incorporate and address any required project changes and/or required threatened and endangered species mitigation measures into its supporting analysis within its individual permit record of decision, and to render a final permit decision consistent with the analysis and requirements of the final BO.   Furthermore, on December 5, 2022, the project sponsor provided revised information related regulated discharges, because of which USACE on December 12, 2022, issued a supplemental public notice soliciting comments on the revised information. Based on both the extension of ESA consultation and the need for additional time to review the project sponsor’s revised information submittal, pursuant to 42 USC § 4370m-2(c)(2)(d)(i)(IV), USACE timely requested Executive Director authorization to modify the Section 10/404 final completion date from February 17, 2023 to April 18, 2023. However, the Executive Director did not sign a determination on the record granting the request by the statutory deadline of January 18, 2023 (30 days prior to the posted completion date). Therefore, USACE could not modify the permitting timetable to reflect the extended completion date. Because USACE was unable to meet the posted completion date, pursuant to 42 USC § 4370m-2(c)(2)(F), USACE appropriately established an alternative completion date for the Section 10/404 action and will adhere to the statutory procedures required by section 4370m-2(c)(2)(F) until the agency takes final action on the Section 10/404 permit.
Current Target Date: