Vineyard Northeast
PERMITTING DASHBOARD PROJECT POSTING DATE: OCTOBER 24, 2023PROJECT WEBSITE: Vineyard Offshore
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Vineyard Northeast proposes to construct and operate the Project located in Lease Area OCS-A 0522, which covers approximately 132,370 acres (ac) and is located approximately 31 miles from Nantucket, Massachusetts and 39 miles from Martha’s Vineyard, Massachusetts.
Offshore components of the Project will consist of up to 160 wind turbine generators (WTG) and electrical service platform (ESP) positions within the Lease Area with one nautical mile spacing between positions. The WTGs and ESPs will be supported by monopiles or piled jacket foundations.
Between the Lease Area and shore, the offshore export cables will be installed within two offshore export cable corridors (OECC), the Massachusetts OECC and the Connecticut OECC.
-
- The Massachusetts OECC will travel from the northernmost tip of the Lease Area to the Horseneck Beach Landfall site in Westport, Massachusetts.
- The Connecticut OECC will travel from the southernmost tip of the Lease Area to three potential landfall sites: Eastern Point Beach, Ocean Beach, and Niantic Beach; all near New London, Connecticut.
Onshore components of the Project will include export cable landfall areas, high-voltage direct current onshore cables, high-voltage alternating current interconnection cables, converter and booster stations, and onshore substation facilities in Massachusetts and Connecticut.
The Executive Director granted a Bureau of Ocean Energy Management request to extend completion dates for all actions on April 18, 2025. The Executive Director Determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management request to extend completion dates for all actions on August 19, 2025. The Executive Director Determination is posted here.
Update:
The Vineyard Northeast Project is paused on the FAST-41 Dashboard until April 1, 2027.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|