Permitting Action Modification History

Planned
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-25-2024 05-26-2026 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-08-2025 07-09-2026 --- No
Publication of Public Notice (Agency Action) 05-23-2025 07-24-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-22-2026 09-13-2027 --- No
Planned
The Section 10/404 milestones are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 119 days results in a commensurate shift to the Section 10/404 action milestones.  Therefore, an extension of the Section 10/404 milestones is requested based upon the extension of BOEM’s EIS milestones.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-25-2024 07-21-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-08-2025 09-04-2025 --- No
Publication of Public Notice (Agency Action) 05-23-2025 09-19-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-22-2026 11-09-2026 --- No
Planned
Date changed from 11/25/24 to 3/24/25 to better align with USACE permitting process.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-25-2024 03-24-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-08-2025 05-08-2025 --- No
Publication of Public Notice (Agency Action) 05-23-2025 05-23-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-22-2026 06-22-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-25-2024 11-25-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-08-2025 05-08-2025 --- No
Publication of Public Notice (Agency Action) 05-23-2025 05-23-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-22-2026 06-22-2026 --- No