USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by craig.litteken… on

Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, were modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Jared Bybee
POC Title:
Bristlecone Field Manager
POC Email:

Description:

The Bureau of Land Management's (BLM) role is to consider authorizing the project through issuance of a right-of-way grant.  As a cooperating agency, the BLM will review the EIS to ensure the analysis is in conformance with the Federal Land Management Policy Act, Ely Resource management Plan, and the 2015 Nevada/Northeastern California Greater Sage grouse land use plan amendment.  Accordingly, a land use plan amendment notification may be required as well as an additional 30 days for Nevada Governor’s office consistency review.

 

Milestones:

Initial application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/23/2027
Current Target Date:
Milestone
Final decision/agency action (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/23/2027
Current Target Date:
Project

PROJECT WEBSITE: https://www.whitepinepumpedstorage.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/21/2027

1 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The proposed 1,000-megawatt closed-loop project would be located in White Pine County, Nevada, and include the construction of two reservoirs, an underground water conveyance system and powerhouse, a 345-kilovolt transmission line, and other project facilities.  The proposed project would be located on federal lands managed by the Bureau of Land Management.

field_status
System Comments
Furthest out
Original Target Date: 07/30/2025
Milestone: Final decision/agency action (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Final decision/agency action (Agency Action) extended by 538
From: 07/30/2025
To: 01/19/2027
Approver Comments
Executive Director determination signed on 3/29/24.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Final decision/agency action (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/23/2027
Current Target Date:
Furthest Original Target Date Milestone
Final decision/agency action (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/23/2027
Current Target Date: