USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, were modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 11-20-2020 11-20-2020 --- Yes
Final decision/agency action (Agency Action) 07-30-2025 01-19-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 11-20-2020 11-20-2020 --- Yes
Final decision/agency action (Agency Action) 07-30-2025 07-30-2025 --- No