USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

In Progress
BLM, as part of its standard process for solar projects, requires several baseline studies before beginning NEPA. The Project Sponsor and BLM have worked together to ensure completeness of the required studies and coordinated to manage BLM review and Project Sponsor submittals to maintain progress. Through recent increased coordination, the agency and Project Sponsor agreed that additional time is needed to finalize and approve the required studies.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 08-11-2025 --- No
Final decision/agency action (Agency Action) 01-16-2026 07-17-2026 --- No
In Progress
Field Office assumed the Final decision/agency action (Agency Action) on the Right-of-Way Authorization (DOI-BLM) was the same date as the date the EA Decision Record and FONSI were signed. The decisions are for two different actions. The actual date that the Field Office is planning that the final decision on the Right-of-Way Authorization will be January 16, 2026.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 01-27-2025 --- No
Final decision/agency action (Agency Action) 01-16-2026 01-16-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 01-27-2025 --- No
Final decision/agency action (Agency Action) 10-31-2025 10-31-2025 --- No