Permitting Action Modification History

In Progress
As part of BLM’s effort to align with the Department of the Interior’s July 15, 2025 memorandum, updates to the Project schedule, including updating the milestone dates on the FAST-41 Dashboard, are necessary to comply with the new requirement that all wind and solar energy project decisions, actions, consultations, and other undertakings be routed through the Office of the Secretary for final review prior to the agency taking action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 09-30-2026 --- No
Final decision/agency action (Agency Action) 01-16-2026 12-06-2027 --- No
In Progress
BLM’s justification for this permitting timetable extension is to account for the additional time needed for the Project Sponsor to complete the cultural resource and bald and golden eagle surveys and BLM to subsequently review the Project Sponsor’s submissions, BLM is requesting an extension of approximately six months for issuance of the final NEPA document and the right-of-way authorization. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 12-17-2025 --- No
Final decision/agency action (Agency Action) 01-16-2026 01-27-2027 --- No
In Progress
BLM, as part of its standard process for solar projects, requires several baseline studies before beginning NEPA. The Project Sponsor and BLM have worked together to ensure completeness of the required studies and coordinated to manage BLM review and Project Sponsor submittals to maintain progress. Through recent increased coordination, the agency and Project Sponsor agreed that additional time is needed to finalize and approve the required studies. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 08-11-2025 --- No
Final decision/agency action (Agency Action) 01-16-2026 07-17-2026 --- No
In Progress
Field Office assumed the Final decision/agency action (Agency Action) on the Right-of-Way Authorization (DOI-BLM) was the same date as the date the EA Decision Record and FONSI were signed. The decisions are for two different actions. The actual date that the Field Office is planning that the final decision on the Right-of-Way Authorization will be January 16, 2026. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 01-27-2025 --- No
Final decision/agency action (Agency Action) 01-16-2026 01-16-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 01-27-2025 --- No
Final decision/agency action (Agency Action) 10-31-2025 10-31-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 07-27-2023 07-27-2023 --- Yes
Completed application received (Agency Action) 01-27-2025 01-27-2025 --- No
Final decision/agency action (Agency Action) 10-31-2025 10-31-2025 --- No