Permitting Action Modification History

Complete
Completed early, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2025 03-04-2026 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 12-19-2025 03-27-2026 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 03-20-2026 04-07-2026 --- Yes
In Progress
completed early, basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2025 03-04-2026 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 12-19-2025 03-27-2026 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 03-20-2026 08-16-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2025 03-04-2026 --- Yes
NOAA Requests Additional Information (Agency Action) 11-14-2025 04-01-2026 --- No
Lead Agency Responds to Additional Information Request/EFH Assessment Resubmitted (Agency Action) 11-28-2025 05-04-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 12-19-2025 06-03-2026 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 03-20-2026 08-16-2026 --- No
Planned
The project sponsor requested the EFH milestones be revised to allow for additional time to conduct the EFH Assessment.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2025 03-04-2026 --- No
NOAA Requests Additional Information (Agency Action) 11-14-2025 04-01-2026 --- No
Lead Agency Responds to Additional Information Request/EFH Assessment Resubmitted (Agency Action) 11-28-2025 05-04-2026 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 12-19-2025 06-03-2026 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 03-20-2026 08-16-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2025 10-31-2025 --- No
NOAA Requests Additional Information (Agency Action) 11-14-2025 11-14-2025 --- No
Lead Agency Responds to Additional Information Request/EFH Assessment Resubmitted (Agency Action) 11-28-2025 11-28-2025 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 12-19-2025 12-19-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 03-20-2026 03-20-2026 --- No