Graphite Creek Project

PERMITTING DASHBOARD PROJECT POSTING DATE: JUNE 02, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/24/2027

3 out of 6

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The Graphite Creek Project is a proposed graphite open pit mine to extract graphite ore and produce a graphite concentrate for further processing and manufacturing of Coated Spherical Graphite, primarily for the electric vehicle lithium-ion battery and energy storage markets, as well as other high grade graphite products.  Graphite ore mined from the Graphite Creek Property, situated on the Seward Peninsula about 37 miles north of Nome, Alaska, would be processed into concentrate at a mineral processing plant to be located adjacent to the mine.

The Executive Director granted a U.S. Army Corps of Engineers request to extend the Essential Fish Habitat (EFH) completion dates on September 26, 2025. The Executive Director determination is posted here.

The Executive Director granted a U.S. Army Corps of Engineers request to extend the Clean Water Act Section 404 permit and the Section 106 of the National Historic Preservation Act review completion dates on July 27, 2026. The Executive Director determination is posted here.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete