USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Environmental Impact Statement (EIS)

Submitted by cori.carraway@… on

Project sponsor provided project updates on 3/13/23. These updates need to be in the DEIS. The two-week delay is to ensure that the DEIS has the new information incorporated.

First DEIS Delay: A complete and sufficient Historic Resources Visual Effects Assessment (HRVEA) and Terrestrial Archaeological Resources Assessment (TARA) and Visual Impact Assessment (VIA) have not been provided by the lessee. Without this data BOEM cannot identify historic properties and assess the effects of the project or conduct necessary Section 106 consultation prior to publication of the draft EIS. The delay to the DEIS delays the FEIS and ROD.

Second DEIS Delay:  on March 13, 2023, ASOW South submitted a revision to the ASOW South Project Design Envelope. This revision needs to be included in the DEIS and consultation documents. Due to this BOEM needed the additional time to incorporate these revisions. The delay to the DEIS delays the FEIS and ROD.

Action
Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
In Progress
POC Name:
Kimberly Sullivan
POC Title:
Environmental Protection Specialist

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
  • Monthly Status Report for June 2024:
    FEIS NOA published on May 31 and BOEM is on track to meet the ROD milestone of July 1.
  • Monthly Status Report for May 2024:
    FEIS NOA on track to publish in the Federal Register on May 31. The FEIS was posted to the BOEM website a week prior to the milestone. BOEM is drafting the ROD in order to meet the July 1 ROD milestone.
  • Monthly Status Report for April 2024:
    BOEM circulated the redline response to agency comment on the preliminary FEIS back to agencies on April 8. BOEM is on track to meet the May 31 milestone.    
  • Monthly Status Report for March 2024:
    BOEM environmental review is on track to meet the May 31 milestone for the DEIS. BOEM is currently addressing agency comment on the preliminary FEIS and will circulate the redline and response to agency comments back to agencies in early April.  
  • Monthly Status Report for February 2024:
    The DEIS milestone was recently shifted to May 31, 2024 and BOEM is on track to meet the milestone. BOEM is currently addressing agency comments on the preliminary FEIS and will circulate the redline and response to agency comments back to agencies in early April, as efforts progress towards towards finalizing the environmental analysis.
  • Monthly Status Report for January 2024:
    BOEM developed a revised timetable for this project after reviewing the project schedule with the cooperating agencies and in consultation with the project sponsor. The revised timetable encompasses all remaining milestones, including milestones for this nonconformant action. While an Executive Director Determination (EDD) is not needed to update this milestone, BOEM intends to adopt the revised timetable, which was provided to the Permitting Council in an EDD request on Jan 26, 2024 and which includes this milestone; upon receipt of the EDD.
  • Monthly Status Report for December 2023:
    BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting timetable for all actions, including this milestone.
  • Monthly Status Report for November 2023:
    Milestone completed on July 19, 2023, potential delay for subsequent milestone of FEIS due to Coastal Zone Management Act. BOEM is working with the Sponsor and NJ Department of Environmental Protection to ascertain impact.
  • Monthly Status Report for October 2023:
    Milestone completed on July 19, 2023, potential delay for subsequent milestone of FEIS due to Coastal Zone Management Act. BOEM is working with the Sponsor and NJ Department of Environmental Protection to ascertain impact.
  • Monthly Status Report for September 2023:
    Milestone Completed on July 19, 2023
  • Monthly Status Report for August 2023:
    Milestone is complete.
  • Monthly Status Report for July 2023:
    Milestone is complete. The draft EIS published in the Federal Register on May 19, 2023.
  • Monthly Status Report for June 2023:
    The availability of the draft EIS published in the Federal Register on May 19, 2023.
  • Non-conformance Explanation:
    BOEM is undertaking a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompasses all NEPA and associated agency actions and milestone dates for the project, including this action. The review is expected to be completed in early May 2023, which will result in coordination with the FPISC Executive Director.
Alternative Completion Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Alternative Completion Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Alternative Completion Date:
Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Alternative Completion Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/16/2024

10 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

The purpose of the Atlantic Shores South (which includes Project 1 and Project 2 or, collectively, the Projects) is to develop two offshore wind energy generation facilities in the Bureau of Ocean Energy Management (BOEM) Lease Area OCSA 0499 to provide clean, renewable energy to the Northeastern U.S. by the mid-to-late 2020s.

System Comments
Furthest out
Original Target Date: 09/29/2023
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)

Requested extensions greater than 30 days for this Action are shown below:

Issuance of Lead Agency Record of Decision (Agency Action) extended by 178
From: 09/29/2023
To: 03/25/2024
Approver Comments
EIS went into nonconformance due to missed date on DEIS (5/5/23). Atlantic Shores South - ED Determination was Final signed 6/15/2023.
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Furthest Original Target Date Milestone
Issuance of Lead Agency Record of Decision (Agency Action)
Alternative Completion Date: