Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 09-30-2021 09-30-2021 --- Yes
Scoping (Agency Action) 11-01-2021 11-01-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-02-2022 05-05-2023 05-19-2023 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 08-04-2023 08-04-2023 05-31-2024 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 09-29-2023 09-29-2023 07-01-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 09-30-2021 09-30-2021 --- Yes
Scoping (Agency Action) 11-01-2021 11-01-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-02-2022 05-05-2023 05-19-2023 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 08-04-2023 08-04-2023 05-31-2024 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 09-29-2023 09-29-2023 07-01-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 09-30-2021 09-30-2021 --- Yes
Scoping (Agency Action) 11-01-2021 11-01-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-02-2022 05-05-2023 05-19-2023 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 08-04-2023 08-04-2023 05-31-2024 No
Issuance of Lead Agency Record of Decision (Agency Action) 09-29-2023 09-29-2023 07-01-2024 No
In Progress
First DEIS Delay: A complete and sufficient Historic Resources Visual Effects Assessment (HRVEA) and Terrestrial Archaeological Resources Assessment (TARA) and Visual Impact Assessment (VIA) have not been provided by the lessee. Without this data BOEM cannot identify historic properties and assess the effects of the project or conduct necessary Section 106 consultation prior to publication of the draft EIS. The delay to the DEIS delays the FEIS and ROD. Second DEIS Delay:  on March 13, 2023, ASOW South submitted a revision to the ASOW South Project Design Envelope. This revision needs to be included in the DEIS and consultation documents. Due to this BOEM needed the additional time to incorporate these revisions. The delay to the DEIS delays the FEIS and ROD. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 09-30-2021 09-30-2021 --- Yes
Scoping (Agency Action) 11-01-2021 11-01-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-02-2022 05-05-2023 05-19-2023 Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 08-04-2023 08-04-2023 02-09-2024 No
Issuance of Lead Agency Record of Decision (Agency Action) 09-29-2023 09-29-2023 03-25-2024 No
In Progress
A complete and sufficient Historic Resources Visual Effects Assessment (HRVEA) and Terrestrial Archaeological Resources Assessment (TARA) and Visual Impact Assessment (VIA) have not been provided by the lessee. Without this data BOEM cannot identify historic properties and assess the effects of the project or conduct necessary Section 106 consultation prior to publication of the draft EIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 09-30-2021 09-30-2021 --- Yes
Scoping (Agency Action) 11-01-2021 11-01-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-02-2022 05-05-2023 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 08-04-2023 08-04-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 09-29-2023 09-29-2023 --- No