Atlantic Shores South
PERMITTING DASHBOARD PROJECT POSTING DATE: APRIL 13, 2021PROJECT WEBSITE: Atlantic Shores Offshore Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE
COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/16/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Environmental Protection Agency
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Civil Works
Description:
The purpose of the Atlantic Shores South (which includes Project 1 and Project 2 or, collectively, the Projects) is to develop two offshore wind energy generation facilities in the Bureau of Ocean Energy Management (BOEM) Lease Area OCSA 0499 to provide clean, renewable energy to the Northeastern U.S. by the mid-to-late 2020s.
Update:
The Executive Director granted a Bureau of Ocean Energy Management request to extend the COP, Section 106, and Section 408 completion dates on June 15, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the OCS Air Permit completion date on October 19, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the Section 106 completion date on November 29, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the COP, Section 106, Section 408, and OCS Air Permit completion dates on February 23, 2024. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management request to extend the Section 408 Permit completion dates on September 10, 2024. The Executive Director determination is posted here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
- Responsible Agency:
- Bureau:
- Action Status:
- SHPO:
- Action Identifier:
- Action Outcome:
| Milestone | Original Target Date | Current Target Date | Milestone Complete |
|---|