The primary driver of the schedule change, as described in the attached justification memo, is a requirement for the applicant’s contractor to recollect and test three additional sediment samples, as the original samples exceeded the holding times specified in their Corps/EPA-approved Sediment Analysis Plan and the Corps/EPA’s 2003 Regional Implementation Agreement, and could not be considered scientifically sound. The memo also describes an additional potential risk to the schedule associated with proposed sediment deposition sites behind Corps levees parallel to the federal navigation channel.
Responsible Agency:
Description:
CURRENT STATUS: The Corps is working with the EIS contractor to complete studies necessary for the integrated Regulatory and 408 Draft Environmental Impact Statement. The delay in receiving the information from PCCA, which was requested in April 2020, and subsequent required sequential modeling has delayed the overall project schedule 12 months.
PRIMARY ISSUE(S): The project’s purpose is to safely navigate fully laden VLCCs from Harbor Island to the Gulf of Mexico and reduce lightering requirements. Based on two navigation studies and ship simulations submitted by the applicant, the proposed project does not meet the stated purpose of safely navigating full laden VLCCs except in limited sea conditions. The previous studies were performed without properly calibrated and validated current velocities, utilized the wrong channel geometry, and employed undersized or lower horsepower tugs that prevented an accurate representation of controlling and handling vessel transit, maneuvering, and berthing. Currently, the type of escort tug that has the necessary performance characteristics required to safely maneuver the proposed vessel does not exist in the world's tug fleet and the level of uncertainty regarding vessel/current interaction is significant.
BACKGROUND/CONTEXT: This project was determined to be a covered project under Title 41 of the Fixing America’s Surface Transportation Act (FAST-41) and added to the Permitting Dashboard as of June 2019. PCCA proposes to deepen the Corpus Christi Ship Channel (CCSC), a federal project, to -81 feet MLLW to Harbor Island and extend the terminus an additional 29,000 feet into the Gulf of Mexico. The dredging will generate 48 MCY of material requiring placement. PCCA has requested use of the ocean dredged material disposal site (ODMDS) as well as several private and federal placement areas which may result in impacts to the federal project as well as special aquatic sites, such as wetlands and seagrass beds.
Milestones:
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 01/13/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 02/10/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 11/28/2022
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 01/13/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 02/10/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 11/28/2022
PROJECT WEBSITE: USACE website for the Port of Corpus Christi Authority Channel Deepening EIS Pr…
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Ports and Waterways
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
CURRENT STATUS: The Corps is working with the Project Sponsor and EIS Contractor to respond to comments on the integrated Regulatory and 408 Draft Environmental Impact Statement.
PURPOSE: The project’s purpose is to safely, efficiently, and economically export current and forecasted crude oil inventories via Very Large Crude Carriers (VLCC), a common vessel in the world fleet. Crude oil is delivered via pipeline from the Eagle Ford and Permian Basins to multiple locations at the Port of Corpus Christi. Crude Oil inventories exported at the Port of Corpus Christi have increased from 280,000 barrels per day in 2017 to 1,650,000 barrels in January 2020 with forecasts increasing to 4,500,000 barrels per day by 2030. Current facilities require vessel lightering to fully load a VLCC which increases cost and effects safety.
BACKGROUND/CONTEXT: This project was determined to be a covered project under Title 41 of the Fixing America’s Surface Transportation Act (FAST-41) and added to the Permitting Dashboard as of June 2019. PCCA proposes to deepen the Corpus Christi Ship Channel (CCSC), a federal project, to -81 feet MLLW to Harbor Island and extend the terminus an additional 29,000 feet into the Gulf of Mexico. The dredging will generate 48 MCY of material requiring placement. PCCA has requested use of the ocean dredged material disposal site (ODMDS) as well as several private and federal placement areas.
Update:
The Executive Director granted a U.S. Army Corps of Engineers request to extend the Section 106 Review completion date on June 14, 2022. The Executive Director determination is posted here.
The Executive Director granted a U.S. Army Corps of Engineers second request to extend the Section 106 Review completion date on September 15, 2022. The Executive Director determination is posted here.
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 01/13/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 02/10/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 11/28/2022
-
Endangered Species Act Consultation (DOI-FWS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 01/13/2023 -
Endangered Species Act Consultation (NOAA-NMFS)
:
ESA Consultation Concludes (Agency Action)
- Completed Date: 12/12/2022 -
Section 106 Review
:
Section 106 consultation concluded (Agency Action)
- Completed Date: 02/10/2023 -
Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Consultation
:
NOAA Issues any EFH Conservation Recommendations (Agency Action)
- Completed Date: 11/28/2022
Original Target Date: 04/15/2022
Milestone: Issuance of Lead Agency Record of Decision (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
Issuance of Lead Agency Record of Decision (Agency Action) extended by 824
From: 05/17/2023
To: 07/17/2024