Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-07-2020 04-07-2020 --- Yes
Scoping (Agency Action) 05-15-2020 05-14-2020 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-15-2021 06-10-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 01-14-2022 03-22-2024 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 04-15-2022 07-17-2024 --- Yes
In Progress
Ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-07-2020 04-07-2020 --- Yes
Scoping (Agency Action) 05-15-2020 05-14-2020 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-15-2021 06-10-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 01-14-2022 03-22-2024 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 04-15-2022 07-17-2024 --- No
In Progress
The primary driver of the schedule change, as described in the attached justification memo, is a requirement for the applicant’s contractor to recollect and test three additional sediment samples, as the original samples exceeded the holding times specified in their Corps/EPA-approved Sediment Analysis Plan and the Corps/EPA’s 2003 Regional Implementation Agreement, and could not be considered scientifically sound.  The memo also describes an additional potential risk to the schedule associated with proposed sediment deposition sites behind Corps levees parallel to the federal navigation channel.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-07-2020 04-07-2020 --- Yes
Scoping (Agency Action) 05-15-2020 05-14-2020 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-15-2021 06-10-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 01-14-2022 04-10-2024 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 04-15-2022 07-17-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 04-07-2020 04-07-2020 --- Yes
Scoping (Agency Action) 05-15-2020 05-14-2020 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 03-15-2021 06-10-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 01-14-2022 02-10-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 04-15-2022 05-17-2023 --- No