BOEM still needs to submit the final BA and information required to initiate consultation under ESA due partly to delays in receiving analysis from the developer.
Cooperating under NEPA
Description:
Section 7(a)(2) of the Endangered Species Act (ESA) requires Federal agencies to consult with NOAA Fisheries when any action they authorize, fund, or carry out may affect an ESA-listed species or designated critical habitat under NOAA Fisheries’ jurisdiction. ESA-listed species occur in the action area for the Park City project. The proposed action may affect these resources, therefore Section 7 consultation is required.
This initial permitting timetable for Vineyard Wind 2 reflects the best estimates of the agencies based on past singular offshore wind projects, but is likely to vary, depending on the receipt of sufficient required information from the project sponsor, and the number and timing of concurrent projects.
Milestones:
-
Monthly Status Report for January 2024:BOEM anticipates NMFS will conclude the ESA consultation on February 16, 2024. This aligns with the updated permitting timetable provided to the Permitting Council as part of an Executive Director Determination (EDD) request in December. While this milestone did not need an EDD to be updated, it was included in the revised permitting timetable in the EDD request. BOEM received the EDD on Jan 12, 2024.
-
Monthly Status Report for December 2023:BOEM completed a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. BOEM provided the Permitting Council with an updated permitting timetable on Dec 15, 2023 for all actions, including this milestone.
-
Monthly Status Report for November 2023:BOEM will complete a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. BOEM will provide the Permitting Council with an updated permitting timetable on Dec 15 for all actions, including this milestone.
-
Monthly Status Report for October 2023:BOEM will complete a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. BOEM will provide the Permitting Council with an updated permitting timetable on Dec 15, 2023 for all actions, including this milestone.
-
Monthly Status Report for September 2023:Consultation package was submitted Sept 7, 2022 and deemed complete on June 15, 2023.
-
Monthly Status Report for August 2023:milestone is complete
-
Monthly Status Report for July 2023:On June 15, 2023, NMFS deemed the ESA consultation request package complete
-
Monthly Status Report for June 2023:On June 15, 2023 NMFS deemed the ESA consultation request package submitted complete.
-
Monthly Status Report for May 2023:BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on April 11, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On May 10, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the Executive Director did not have enough time to make a decision more than 30 days in advance of the completion date of this action, as required under the FAST-Act (42 U.S.C. § 4370m-2(c)(2)(D)(ii)), this action was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
-
Monthly Status Report for April 2023:Milestone is complete
-
Monthly Status Report for March 2023:BOEM submitted the updated BA to NOAA on March 10, 2023. BOEM anticipates receiving comments from NOAA NMFS on or around April 7, 2023. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for February 2023:BOEM has delayed submittal of the updated BA to NOAA NMFS (anticipated for submittal on February 21, 2023) until information is received from the project sponsor in response to NOAA NMFS comments on the Marine Mammal Protection Act Letter of Authorization application updates and BOEM comments on the hydroacoustic analysis to ensure consistency among both ESA and MMPA processes. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for January 2023:BOEM has delayed submittal of the updated BA to NOAA NMFS (originally anticipated for submittal on December 23, 2022) until February 21, 2023. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for December 2022:BOEM is delaying submittal of the updated BA to NOAA NMFS (originally anticipated for submittal on December 23, 2022) and currently coordinating with NOAA NMFS regarding schedule implications. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for November 2022:On November 7, 2022, BOEM received comments from NOAA NMFS on the draft BA. BOEM is currently reviewing these comments. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for October 2022:On September 7, 2022, BOEM submitted the initial Biological Assessment (BA) to NOAA NMFS. BOEM is anticipating comments from NOAA NMFS on the BA by November 7, 2022. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Monthly Status Report for September 2022:On September 7, 2022, BOEM submitted the initial Biological Assessment (BA) to NOAA NMFS (concurrently with the preliminary draft Environmental Impact Statement for cooperating agency review) and requested Endangered Species Act (ESA) consultation with NOAA NMFS. Therefore, the milestone “ESA Consultation Request Package Submitted” was marked complete on September 7, 2022. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will continue to submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation is complete.
-
Non-conformance Explanation:BOEM missed the completion date for NOAA NMFS Milestone “ESA Consultation Request Package Submitted,” which was scheduled for completion on July 29, 2022, because BOEM did not timely receive confirmation of a delay in the delivery of the draft Biological Assessment (BA) from its third party contractor in order to request to revise the completion date prior to 30 days of the original completion date pursuant to 43 U.S.C. 4370m-2(c)(2)(D)(ii). The delay in BOEM receiving the draft EFH assessment from its third-party contractor for the New England Wind Project has in turn resulted in a corresponding delay for the initiation of Endangered Species Act (ESA) Section 7 consultation with NOAA NMFS. Reasons for the third party contractor’s delay in delivering the draft BA to BOEM include delays in the National Environmental Policy Act process resulting from an extended alternatives development period, recent project modifications and additional information filed by the project sponsor, and revising the relevant information in the BA to be consistent with updated project information resulting from NOAA NMFS reviews of the project’s Marine Mammal Protection Act (MMPA) Letter of Authorization (LOA) Application. Pursuant to 42 U.S.C. 4370m-2(c)(2)(F)(ii)(III), BOEM will submit to the Permitting Council Executive Director monthly reports on all BOEM activities related to ESA consultation with NOAA NMFS until the final milestone for ESA consultation (the affected environmental review or authorization) is complete. BOEM currently estimates an alternate completion date of September 2, 2022.
This target timeline is dependent on receipt of a consultation request from BOEM, consisting of a Biological Assessment, that considers effects of all proposed Federal actions. Receipt of the consultation request is set concurrent with the beginning of the cooperating agency review of the draft NEPA document.
-
Environmental Impact Statement (EIS)
:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
- Completed Date: 12/23/2022
This date is dependent upon NOAA Fisheries receiving sufficient information from BOEM to deem the package complete and initiate the ESA consultation. This includes receipt of a complete final Biological Assessment (preferably as an appendix to the DEIS), the proposed MMPA Incidental Take Authorization from NMFS, and the public availability of the DEIS. (Note that this date anticipates considerable coordination with BOEM on review of a draft BA). This date is set at least 60 days after the NOA for DEIS and no sooner than 30 days before the publication of the proposed MMPA ITA to allow adequate time to review the incoming materials and ensure receipt of complete information prior to initiation of consultation.
The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation. This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS. The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).
The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation. This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS. The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/22/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Description:
Update: In October 2021, the project name changed from Vineyard Wind South to New England Wind to reflect restructuring of the project’s parent companies (for more information, see Vineyard Wind’s September 21, 2021 press release).
New England Wind is the proposal to develop offshore renewable wind energy facilities in BOEM Lease Area OCS-A 0534 along with associated offshore and onshore cabling, onshore substations, and onshore operations and maintenance (O&M) facilities. Park City Wind LLC, a wholly owned subsidiary of Avangrid Renewables, LLC, is the Proponent and would be responsible for the construction, operation, and decommissioning of New England Wind. New England Wind will be developed in two Phases. If approved, Phase 1, also known as the Park City Wind project, will be developed in the northeastern portion of Lease Area OCS-A 0534. Phase 2, also known as Commonwealth Wind, will be located southwest of Phase 1.
FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at https://www.permits.performance.gov/fpisc-content/fast-41-process.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the NEPA, COP, Section 106, Sections 10/404, and OCS air permit actions completion date on May 10, 2023. The Executive Director determination is posted here.
The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation. This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS. The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).
The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation. This date must be prior to issuance of the MMPA ITA Publication of Final Regulations (for a LOA) or MMPA Decision Rendered (if IHA) and publication of the NOA of FEIS. The target completion date is at least 150 days following the consultation initiation date (135 day regulatory timeline plus 15 days to allow for BOEM review of the draft Opinion).
Original Target Date: 04/24/2023
Milestone: ESA Consultation Concludes (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
ESA Consultation Concludes (Agency Action) extended by 150
From: 09/21/2023
To: 09/21/2023