Lead agency changed during the lockout period; ED granted exemption to the lockout for that reason.
Milestones:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/11/2027
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Conventional Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Land Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Description:
The Black Bear Natural Gas Development Project is located in the Angelina National Forest in San Augustine County, Texas and includes up to four gas well pads, access roads to the well pads, a main trunk pipeline for the transportation of natural gas and gathering pipelines connecting the well pads. Each well pad will have up to eight proposed wells that will be horizontally drilled into both private and U.S. Department of the Interior’s Bureau of Land Management (BLM) managed minerals with the intent of producing primarily natural gas.
Original Target Date: 11/13/2026
Milestone: ESA Consultation Concludes (Agency Action)
Requested extensions greater than 30 days for this Action are shown below:
ESA Consultation Concludes (Agency Action) extended by 71
From: 11/13/2026
To: 01/23/2027